PROJECT TITLE:  ANIMAL SHELTER — EXPANSION/ RENOVATION                     PROJECT CODE:  FM2409

           NET EFFECTS ON OPERATING      AND                    TOTAL ESTIMATED    CAPITAL COST:
           MAINTENANCE    COST (+   OR -)  ANNUAL:

           Direct Operating Cost                                Professional  Services $                 450, 000

           Personnel:       Full Time                           Construction $                         4, 750, 000
                            Part Time $                       0 Testing &  Material Services $           125, 000
           Total Salary $                                     0  Furniture,   Fixtures &   Equip. $      600, 000
           Purchase of Services                                 Contingency $                            450, 000

           Materials &  Supplies                                Temporary Animal Shelter $               150, 000
           Utilities






                                                              0
           Subtotal:                                          0 Total Estimated Capital Cost $         6, 525, 000

           Maintenance  Costs                                   Funding Source:
                                                                Transfer  from:
                                                                Car Rental Fund                        6, 275, 000


                                                              0

           Subtotal: $                                        0 Additional Funding Needed:
                                                                Transfer  from:
                                                                General CIP Fund Balance                 250, 000
           Total Estimated Annual Cost $                      0 Total Funding                          6, 525, 000
                                                   CURRENT     STATUS
                                                                               OVER/ UNDER
           PHASE/ FUNDING  SOURCE                      BUDGET      EXPENDED     BUDGET (- +) %        EXPENDED
          Professional  Services $                      450, 000 $    363, 772 $      86, 228              81
          Construction $                              4, 750, 000 $  1, 375, 069 $  3, 374, 931            29%
          Testing &  Material Services $                125, 000 $     31, 144 $      93, 856              25%
          Furniture,  Fixtures &  Equipment $           600, 000 $     10, 542 $    589, 458                2%
          Contingency $                                 450, 000 $          0 $     450, 000                0%
          Temporary Animal Shelter $                    150, 000 $    121, 937 $      28, 063              81%












           TOTAL  PROJECT                             6, 525, 000 $  1, 902, 464 $  4, 622, 536            29%