Capital Project Request
Department: FLEET & FACILITY OPERATIONS Date Prepared: May 07,2007
Submitted By: KYLE MCADAMS Date Completed:
Project Title: ANIMAL SHELTER — EXPANSION/ RENOVATION
Project Type: FACILITIES Sub -Type: REMODEL
Project Code: FM2409 Priority: A
COUNCIL AUTHORIZATION:
October 10, 2023: Authorized the City Manager to negotiate and execute an Architectural Services Contract with
Oxley Williams Tharp Architects for the design, renovation, and construction of the Animal Services facility. The
estimated expenditure is $ 405, 000.
November 26, 2024: Awarded Request for Competitive Sealed Proposal ( RFCSP) No. 001- 25 for the
construction and remodel of the Animal Shelter in the amount of $4, 641, 000, authorized an owner -controlled
contingency not to exceed 10 percent, and authorized the City Manager to enter into a construction contract with
Modern Contractors.
RELATIONSHIP TO OTHER PROJECTS AND/ OR MASTER PLAN:
PROJECT DESCRIPTION:
The project consists of a remodel of the former fire station # 2 building and animal shelter facility to better
accommodate animal containment, visitors, adoptions, and animal services. The project scope includes the
addition of multiple enclosed dog runs, quarantine runs, an adoption room, additional room for cat containment,
and an area for animal examination and washing. Office space expansion will be included in the renovation as
well as updates to the public/employee restrooms. Additional space within the facility will also be designed for
potential public works storage.
PROJECT SCHEDULE:
Began Design: January 2024
Design Complete: July 2024
Began Construction: January 2025
Anticipate Construction Complete: February 2026
JUSTIFICATION:
The current animal shelter facility was opened in 1978 and has surpassed its capacity to meet current and future
demands.
Ordinance No. 2432, Page 290 of 474