City of Euless

                                            Capital Project Request


           Department:            FLEET &   FACILITY  OPERATIONS               Date  Prepared:       May 07,2007
           Submitted By:          KYLE  MCADAMS                                Date Completed:
           Project Title:        ANIMAL SHELTER —  EXPANSION/    RENOVATION
           Project  Type:         FACILITIES                  Sub -Type:   REMODEL

           Project Code:          FM2409                      Priority:   A
           COUNCIL  AUTHORIZATION:
            October 10,  2023:  Authorized the City Manager to negotiate and execute an Architectural Services Contract with
            Oxley Williams Tharp Architects for the design,  renovation,  and construction of the Animal Services facility.  The
            estimated expenditure is $ 405, 000.
            November 26,  2024:  Awarded Request for Competitive Sealed Proposal ( RFCSP)  No.  001- 25 for the
            construction  and remodel of the Animal Shelter in the amount of $4, 641, 000,  authorized an owner -controlled
            contingency not to exceed 10 percent,  and authorized the City Manager to enter into a construction contract with
            Modern Contractors.


           RELATIONSHIP   TO OTHER   PROJECTS   AND/ OR MASTER    PLAN:












           PROJECT   DESCRIPTION:
           The project consists of a remodel of the former fire station # 2 building and animal shelter facility to better
            accommodate animal containment,  visitors,  adoptions,  and animal services. The project scope includes the
            addition of multiple enclosed dog runs,  quarantine runs,  an adoption room,  additional room for cat containment,
            and an area for animal examination and washing.  Office space expansion will be included in the renovation as
           well as updates to the public/employee restrooms.  Additional space within the facility will also be designed for
            potential public works storage.




           PROJECT SCHEDULE:
            Began Design:  January 2024
            Design Complete:  July 2024
            Began Construction:  January 2025
           Anticipate Construction Complete:  February 2026





           JUSTIFICATION:
           The current animal shelter facility was opened in 1978 and has surpassed its capacity to meet current and future
           demands.