PROJECT  TITLE:     POLICE &   COURTS BUILDING REMODEL            PROJECT   CODE:   FM2312

             NET EFFECTS  ON OPERATING   AND                 TOTAL ESTIMATED   CAPITAL  COST:
             MAINTENANCE   COST (+  OR -)  ANNUAL:
                                                             Professional  Services                   1, 210, 000
             Direct  Operating  Cost                         Construction                            21, 971, 524
             Personnel:          Full Time                   Furniture,  Fixtures &  Equipment        3, 131, 800
                                 Part Time                 0 Testing &  Material  Services              250, 000
             Total Salary                                  0 Contingency                              1, 501, 436
             Purchase of Services
             Materials &   Supplies
             Utilities

             Avg.  Annual Debt Service              1, 889, 000



             Subtotal:                              1, 889, 000 Total  Estimated  Capital  Cost      28, 064, 760
                                                             FUNDING  SOURCE:
             Maintenance  Costs
                                                             Transfer  from:
                                                             CCPD Operating Fund                      2, 210, 000
                                                             Equipment  Replacement  Fund             1,  834,  236

                                                             2023  Certificates  of Obligation       22, 000, 000
                                                           0 Interest Earnings                        2, 020, 524
             Subtotal:                                     0


             Total Estimated  Annual  Cost          1, 889, 000 Total Funding                        28, 064, 760

                                                    CURRENT    STATUS
                                                                                 OVER/ UNDER
             PHASE/ FUNDING  SOURCE              BUDGET          EXPENDED        BUDGET (- +)      EXPENDED
             Professional  Services                1, 210, 000         901, 903        308, 097            75%
             Construction                         21, 971, 524       7, 476, 658     14, 494, 866          34%
             Furniture,  Fixtures &   Equipment    3, 131, 800         150, 369       2, 981, 431           5%
             Testing &  Material  Services           250, 000                0         250, 000             0%
             Contingency                           1, 501, 436               0        1, 501, 436           0%























             TOTAL PROJECT                        28, 064, 760       8, 528, 930 $   19, 535, 830          30%