Business Plan





                             Preserve Financial Stability and Resilience
                                         Maintain Availability of City Resources
                         Project                   Performance Measure(s)                Department(s)
             Enterprise IT Project (FY 2023) –   Project Completion            Information Technology
             eBuilder Integration with Workday


             Summary:                                                                 Estimated
             Integrations must be considered for the following      Milestone        Completion       Status
             program/project areas:                            Project Charter     2  Qtr. FY 2024    Complete
                                                                                    nd
                                                               Planning Phase      4  Qtr. FY 2024   Complete
                                                                                    th
                •  Program budget management                   Procure Phase 1 –   4  Qtr. FY 2024   Complete
                                                                                    th
                •  Project creation                            Consulting
                •  Project budget management                   eBuilder Business   2  Qtr. FY 2025   Complete
                                                                                    nd
                •  Budget transfers                            Analysis
                •  Budget amendments or changes                Procure Phase 2 –   3  Qtr. FY 2025   Complete
                                                                                    rd
                •  Purchase order and contract creation        eBuilder Integration
                •  Invoice payment                             Services
                                                               Design Phase        4 Qtr. FY 2025   In progress
                                                                                    th
             In addition to these specific processes that are no longer   Build Phase
             integrated with eBuilder and the City's financial system,   Implementation Phase
             the implementation of Workday has also resulted in the   Project Closure
             loss of process controls put in place in response to Audit
             findings are not configurable in Workday.




                             Preserve Financial Stability and Resilience
                                         Maintain Availability of City Resources

                        Project                  Performance Measure(s)                  Department(s)
             Enterprise IT Project (FY 2023) –   Project Completion            Information Technology, Police
             PD Law Enforcement Internal
             Records and Performance
             Solution

             Summary:                                                                 Estimated
             The Police Department (APD) utilizes Administrative    Milestone        Completion       Status
             Investigations Management (AIM) to manage various   Project Charter   1  Qtr. FY 2024    Complete
                                                                                    st
             agency activities but must find a replacement as   Planning Phase     3  Qtr. FY 2025    In Progress
                                                                                    rd
             Benchmark Analytics, AIM's new owner, plans to sunset   Procure Phase   2  Qtr. FY 2025    Complete
                                                                                    nd
             the platform and migrate clients to a costlier product that   Design/Build Phase   3  Qtr. FY 2025    In Progress
                                                                                    rd
             doesn’t meet APD’s needs or budget. This project will   Data Conversion/   1  Qtr. FY 2026
                                                                                    st
             define APD’s requirements and follow the City’s   Migration
             procurement process to select a suitable alternative.   Implementation Phase  1  Qtr. FY 2026    Pending
                                                                                    st
                                                               Project Closure     2  Qtr. FY 2026
                                                                                    nd


                                                              Note on Schedule Change:
                                                              The project phases are aligned with vendor planning activities.