Page 396 - CityofArlingtonFY26AdoptedBudget
P. 396

Infrastructure

                                      Goal 1: Plan, Manage, and Maintain Public Assets
                                    Objective 2: Maintain City Standards for all Municipal Buildings
                        Project                     Performance Measure(s)                 Department(s)
             Core  New Traffic Management    Overall Satisfaction of Project Management  Asset Management and Public
             INF   Center                   Project Completion on Time and at Budget  Works
             1.2.7
             Summary:
                                                                  Milestone            Estimated     Actual
             The City’s Traffic Management Center needs to                            Completion   Completion
             relocate from the Ott Cribbs Public Safety Center   Initial Project     May 2025      June 2025
             into a larger space. The project goals include to   Schedule/Development
             identify, and if needed acquire, an existing building   Phase
             to remodel. The remodeled facility will house office   Request for Qualifications for   June 2025
             space to include eight offices, 10 cubicle spaces,   Architect/Engineer
             and 6-10 workstations. Additionally, space would   Architect/Engineer Selection   Fall 2025
             be made available for 30 workstations to     Process
             accommodate field staff, including a conference   Council Approval of Architect   Fall 2024
             room, a break room and work area. A server closet   Contract
             and back-up generator also is required for the   Design Phase           Summer
                                         st
             facility. The target completion is 1  Quarter FY                        2025
             2026 so that the center is operational by January or   Finalize Construction   Winter 2025
             February 2026 in time for the World Cup.     Documents
                                                          Permit Phase               Winter 2025
             Update:                                      Bidding Phase              Winter 2025
                   rd
             In the 3  Quarter, City staff developed a
                                                          Construction Begins        Spring 2026
             preliminary plan to locate the Traffic Management   Construction Complete   Spring 2026
                          th
             Center on the 4  floor of the City Tower. A Request
             for Qualifications will be issued in July to short-
             listed architect firms. Design is scheduled to begin
             in September 2025.