Infrastructure
Goal 1: Plan, Manage, and Maintain Public Assets
Objective 2: Maintain City Standards for all Municipal Buildings
Project Performance Measure(s) Department(s)
Core Fire Station #8 • Overall Satisfaction of Project Management Asset Management and Fire
INF Rebuild • Project Completion on Time and at Budget
1.2.2
Summary:
Milestone Estimated Actual
In November 2018, Arlington voters approved Completion Completion
general obligation bonds for the reconstruction of Issue a RFQ for Architects Spring 2022 Spring 2022
Fire Station #8. The Arlington Fire Department has Select an Architect for Design Summer 2022 Fall 2022
partnered with Asset Management to re-design Council Approval of Architect Fall 2022 Fall 2022
the existing facility located at 2004 Madison Contract
Drive. The station is at the north part of the City Design Phase Summer 2023 Fall 2023
and built in 1978 and is currently managed by the Site Permit Phase Summer 2023 Dec. 2023
Fire Department and was most recently Bidding Phase Fall 2023 Summer 2024
remodeled in 2018.
Building Permit Phase Summer 2023 Summer 2024
Construction Phase start Fall 2024 Fall 2024
Update:
rd
In the 3 Quarter, concrete work, building steel Move In Fall 2025
structure, masonry walls, steel floor and roof
decking were completed.
97