Page 390 - CityofArlingtonFY26AdoptedBudget
P. 390
Infrastructure
Goal 1: Plan, Manage, and Maintain Public Assets
Objective 2: Maintain City Standards for all Municipal Buildings
Project Performance Measure(s) Department(s)
Core Police Evidence Storage, Crime Overall Satisfaction of Project Management Asset Management and Police
INF Lab & North District Substation Project Completion on Time and at Budget
1.2.1
Summary:
Milestone Estimated Actual
In November 2018, Arlington voters approved Completion Completion
general obligation bonds to design and build a new Initial Project May 2021 Jan. 2022
Police Evidence Storage Facility. In Winter of 2021, Schedule/Development Phase
City Council approved the purchase of a Request for Qualifications for June 2021 Feb. 2022
commercial property at 1715 E. Lamar Blvd. Architect/Engineer
This property will be converted into a new facility Architect/Engineer Selection Spring 2022 June 2022
for the Police Department that will house a North Process
District substation, evidence storage and crime lab. Council Approval of Architect Spring 2022 June 2022
Contract
Update: Design Phase Summer 2023 Fall 2023
rd
In the 3 Quarter, a construction cost was Finalize Construction Fall 2023 Summer 2024
negotiated with Spawglass Construction and staff Documents
prepared the contract for City Council review and Permit Phase Winter 2023 Summer 2024
approval for the June 24, 2025 meeting.
Bidding Phase Summer 2024 Feb. 2025
Construction Begins Summer 2025
Finalize Selection of Fixtures, Fall 2025
Furniture, and Equipment
Construction Complete Spring 2026
96