Infrastructure

                                      Goal 1: Plan, Manage, and Maintain Public Assets
                                    Objective 2: Maintain City Standards for all Municipal Buildings
                          Project                       Performance Measure(s)               Department(s)
             Core  Police Evidence Storage, Crime    Overall Satisfaction of Project Management  Asset Management and Police
             INF   Lab & North District Substation    Project Completion on Time and at Budget
             1.2.1
             Summary:
                                                                  Milestone            Estimated     Actual
             In November 2018, Arlington voters approved                              Completion   Completion
             general obligation bonds to design and build a new   Initial Project    May 2021     Jan. 2022
             Police Evidence Storage Facility. In Winter of 2021,   Schedule/Development Phase
             City Council approved the purchase of a       Request for Qualifications for  June 2021   Feb. 2022
             commercial property at 1715 E. Lamar Blvd.    Architect/Engineer
             This property will be converted into a new facility   Architect/Engineer Selection   Spring 2022   June 2022
             for the Police Department that will house a North   Process
             District substation, evidence storage and crime lab.   Council Approval of Architect  Spring 2022   June 2022
                                                           Contract
             Update:                                       Design Phase              Summer 2023  Fall 2023
                   rd
             In the 3  Quarter, a construction cost was    Finalize Construction     Fall 2023    Summer 2024
             negotiated with Spawglass Construction and staff   Documents
             prepared the contract for City Council review and   Permit Phase        Winter 2023   Summer 2024
             approval for the June 24, 2025 meeting.
                                                           Bidding Phase             Summer 2024  Feb. 2025
                                                           Construction Begins       Summer 2025
                                                           Finalize Selection of Fixtures,  Fall 2025
                                                           Furniture, and Equipment
                                                           Construction Complete     Spring 2026