Enhance Regional Mobility
Goal 2: Plan, Manage, and Maintain Public Transportation Infrastructure
Objective 1: Optimize Effectiveness and Efficiency of Existing Transportation System
Project Performance Measure(s) Department(s)
ERM I-30 and SH-360 Interchange Overall satisfaction with the Management Public Works
2.1.2 of Traffic Flow During Peak Hours
Summary:
Estimated Actual
Milestone
The purpose of this TxDOT project is to improve traffic Completion Completion
safety and reduce traffic congestion at the interchange of Package A Construction Spring 2023
Interstate 30 and State Highway 360. Formerly a toll road Package B Construction Spring 2023 Dec. 2023
loop interchange, the new infrastructure will include main Package C Construction Pending
lane improvements and direct connection ramps to each Package D Construction Pending
facility. Package E Construction Summer 2020 Apr. 2021
This project is split into the following five construction
phases:
• Package A: Reconstruction of the Six Flags Drive
Bridge over I-30
• Package B: I-30/SH-360 interchange
improvements
• Package C: Great Southwest Industrial District
railroad bridge crossing just south of Randol Mill
Road
• Package D: Randol Mill Road interchange
improvements
• Package E: Improvements from Abram Street to
I-20
Update:
The City is attending weekly coordination meetings with
TxDOT and interested parties to receive updates
regarding the closeout of the project. Currently, the City
is coordinating with TxDOT to address remaining issues
on the punch list and complaints from citizens and
businesses. The punch list is expected to be complete by
the end of summer 2025.