Page 327 - CityofArlingtonFY26AdoptedBudget
P. 327
Enhance Regional Mobility
Goal 2: Plan, Manage, and Maintain Public Transportation Infrastructure
Objective 2: Complete Construction Projects in a Timely Manner
Project Performance Measure(s) Department(s)
ERM Street Rebuild Projects Overall Satisfaction with the Public Works
2.2.1 Management of Traffic Flow During
Peak Hours
Summary:
Lane
Roadway Capital Improvements Project
Capital street projects are funded with Street Bonds Miles
and are funded through inclusion in the annual capital Turner Warnell Rd. (Matlock Rd. to Cooper St.) 6.0
budget. Bowman Springs Road (I-20 to Enchanted Bay 1.1
Blvd.)
The projects listed below include carry-over projects Sublett Rd. (City Limits to Joplin Rd.) 1.2
funded in prior years that have not completed Debbie Ln. (W. City limits to SH-360) 4.66
construction, as well as the planned FY 2025 projects. 2021 Residential Rebuild (Shenandoah Dr.) 0.80
Project milestones listed in the table will be updated as Dr. MLK Jr. Dr. (Bardin to Green Oaks) 4.02
they occur during the year. Mansfield Webb Rd. (Silo Rd. to Collins St.) 2.6
Mitchell St. (Collins to Sunnyvale) 0.8
Update:
Mitchell Street (Collins Street To Sunnyvale Drive)
On Debbie Lane Project, 90% of underground utilities (water,
construction contract was approved in City Council sewer & storm drain) are done. Approximately half of Debbie
Meeting of May 13, 2025 Construction is expected to Lane has been paved. Existing asphalt pavement will be
start in July 2025.
removed by end of August.
On Dr. MLK Jr. Dr., Contractor is currently working on
underground utilities, traffic signal work at Bardin Road
and overall site grading. Subgrade stabilization is
anticipated to start the week of July 28, 2025 and
paving operations will begin approximately 2 weeks
after the stabilization starts.
Estimated Actual Bid Estimated Actual
Roadway Capital Improvement Project
Bid Date Date Completion Completion
Harris Rd. (Calender Rd. to Cooper St.) May 2019 Nov. 2020 Oct. 2022 Oct. 2024
Poly Webb Rd. (Pleasant Ridge Rd. to Shorewood Dr.) Oct. 2021 Mar. 2023 Jan. 2025 June 2024
Turner Warnell Rd. (Matlock Rd. to Cooper St.) Oct. 2021 Dec. 2022 May 2025
Sublett Rd. (City Limits to Joplin Rd.) Nov. 2021 Sept. 2022 Nov. 2023
Debbie Ln. (W. City Limits to SH-360) Nov. 2022 Dec. 2022 June 2025
2021 Residential Rebuild (Shenandoah Dr.) Nov. 2022 Feb. 2023 Apr. 2024 Sept. 2024
Dr. MLK Jr. Dr. (Bardin Rd. to Green Oaks Blvd.) Nov. 2023 Oct. 2024 Nov. 2024
Mansfield Webb Rd. (Silo Rd. to Collins St.) Feb. 2024
Mitchell St. (Collins St. to Sunnyvale Dr.) Feb. 2024 Mar.2025 April 2026
33