•  Other projects or buildings where civil engineering is required.

                   11.    Bonding Requirements

                          a.  Bid Bonds

                              A bid bond may be required for a specified amount or a percentage (from
                              1% to 5%) of the total contract  price to  ensure that if a  bidder/offer
                              withdraws the bid/offer after acceptance, the City will not suffer a loss.

                          b.  Performance and Payment Bonds

                              Required for public works contracts.  The contractor, before beginning the
                              work, must execute required bonds that are payable to the City of Haslet:

                              •  Performance bond, conditioned on faithful performance of the work in
                                 accordance with the  plans, specifications,  and contract documents if
                                 the contract is in excess of $100,000; and
                              •  Payment bond if the contract is in excess of $25,000

                              Bonds must be in the full amount of the contract price and executed by a
                              surety company authorized to do business in the state of Texas.

               12.     Change Orders

                       A change order is a written order signed by the project engineer/manager, and
                       approved d by the City, directing the contractor to make changes in the plans and
                       specifications or decreasing or increasing the quantity of work to be performed or
                       of  materials, equipment or supplies to be furnished authorized by the changes
                       clause of the   contract.

                       Requirements:

                       •  All changes to the contract must be in writing.
                       •  The City Manager may approve change orders up to $15,000, subject to City
                          Council ratification.
                       •  The original contract price may not be increased by more than 25%.
                       •  The original contract price may not be decreased by more than 25% without
                          the contractor’s consent.
                       •  Total contract price may not be increased unless the cost of the change can
                          be paid  from available  funds or is provided  for by the authorization of the
                          issuance of time warrants.


               Purchasing Policies                                                                   Page 21

               Haslet Adopted Budget FY 2024-2025                                                         414
   411   412   413   414   415   416   417   418   419   420   421