Page 92 - FY 2025 Adopted Operating Budget and Business Plan
P. 92
Business Plan Return to Table of Contents
Culture/Recreation/Education
Goal 1: Provide Activities, Educational Opportunities, and Services that Meet the Needs of the
Community
Objective 1: Develop and Implement Programming Based on the Needs of the Community
Project Performance Measure(s) Department(s)
Core ACTIV – Active Adult • Overall Satisfaction of Project Management Asset Management and
CRE Center Construction • Project Completion on Time and at Budget Parks & Recreation
1.1.1 • Citizen Satisfaction with Overall Quality of Parks
and Recreation Programs and Classes
Summary:
Milestone Estimated Actual
In a special election on May 6, 2017, Arlington voters Completion Completion
approved obligation bonds to build an Active Adult Initial Project Jan. 2019 Jan. 2019
Center. This new facility for residents 50 years of age and Schedule/Development
older will be located on the southwest corner of the Phase
Pierce Burch Water Treatment site on Green Oaks Architect/Engineer RFQ July 2019 July 2019
Boulevard between W. Arkansas Lane and W. Pioneer Architect/Engineer Oct. 2019 Dec. 2019
Parkway. Selection Process
Council Approval of Dec. 2019 Mar. 2020
Architect Contract
CMAR Delivery Method Fall 2019 Jan. 2020
Council Approval
Finalize Construction Fall 2022 Fall 2022
Documents
Permit Process Fall 2022 Fall 2022
Guaranteed Maximum Fall 2022 Fall 2022
Price to Council
Construction Begins Winter 2022 Jan. 2023
Finalize Selection of Fall 2023 June 2023
Furniture and Equipment
Construction Complete Winter 2024
FY 2025 Adopted Budget and Business Plan 83 City of Arlington, Texas