Page 408 - FY 2025 Adopted Operating Budget and Business Plan
P. 408

Return to Table of Contents




                                           Enhance Regional Mobility

                          Goal 2: Plan, Manage, and Maintain Public Transportation Infrastructure
                                    Objective 2: Complete Construction Projects in a Timely Manner
                         Project                   Performance Measure(s)                 Department(s)
             ERM   Street Rebuild Projects   Overall Satisfaction with the     Public Works
             2.2.1                           Management of Traffic Flow During
                                             Peak Hours
             Summary:
                                                                                                         Lane
                                                                 Roadway Capital Improvements Project
             Capital street projects are funded with Street Bonds                                        Miles
             and are funded through inclusion in the annual capital   Harris Road (Calender Rd. to Cooper St.)   2.2
             budget.                                         Poly Webb Rd. (Pleasant Ridge Rd. to Shorewood   1.0
                                                             Dr.)
             The projects listed below include carry-over projects   Turner Warnell Rd. (Matlock Rd. to Cooper St.)   6.0
             funded in prior years that have not completed   Bowman Springs Road (I-20 to Enchanted Bay   1.1
             construction, as well as the planned FY 2024 projects.   Blvd.)
             Project milestones listed in the table will be updated as   Sublett Rd. (City Limits to Joplin Rd.)   1.2
             they occur during the year.                     Debbie Ln. (W. City limits to SH-360)       4.66
                                                             2021 Residential Rebuild (Shenandoah Dr.)   0.80
             Update:                                         Dr. MLK Jr. Dr. (Bardin to Green Oaks)      4.02
             Dr. MLK Jr. Dr. Project had bid opening on October 11,
                                                             2022 Residential Rebuild Phase I             0.9
             2024.  Construction contract is being prepared for   2022 Residential Rebuild Phase II       1.6
             award in City Council meeting of October 22, 2024.    Mansfield Webb Rd. (Silo Rd. to Collins St.)   2.6
             Construction is estimated to start in December 2024.
                                                             Mitchell St. (Collins to Sunnyvale)          0.8





                                                               Estimated    Actual Bid   Estimated    Actual
                     Roadway Capital Improvement Project
                                                                Bid Date      Date      Completion   Completion
               Harris Rd. (Calender Rd. to Cooper St.)        May 2019    Nov. 2020     Oct. 2022
               Poly Webb Rd. (Pleasant Ridge Rd. to Shorewood Dr.)   Oct. 2021   Mar. 2023   Jan. 2025
               Turner Warnell Rd. (Matlock Rd. to Cooper St.)   Oct. 2021   Dec. 2022   May 2025
               Bowman Springs Rd. (I-20 to Enchanted Bay Blvd.)   Nov. 2021   Mar. 2022   Sept. 2023   Jan. 2024
               Sublett Rd. (City Limits to Joplin Rd.)        Nov. 2021   Sept. 2022    Nov. 2023
               Debbie Ln. (W. City Limits to SH-360)          Nov. 2022   Dec. 2022     June 2025
               2021 Residential Rebuild (Shenandoah Dr.)      Nov. 2022   Feb. 2023     Apr. 2024
               Dr. MLK Jr. Dr. (Bardin to Green Oaks)         Nov. 2023
               2022 Residential Rebuild Phase I               Dec. 2023   April 2024    Mar. 2025
               2022 Residential Rebuild Phase II              Dec. 2023   Feb 2024      Mar. 2025
               Mansfield Webb Rd. (Silo Rd. to Collins St.)   Feb. 2024
               Mitchell St. (Collins to Sunnyvale)            Feb. 2024




















                                                             35