                                           Enhance Regional Mobility

                          Goal 2: Plan, Manage, and Maintain Public Transportation Infrastructure
                           Objective 1: Optimize Effectiveness and Efficiency of Existing Transportation System
                          Project                  Performance Measure(s)                 Department(s)
             ERM   Safety Action Plan         Completion of Plan               Transportation
             2.1.4
             Summary:
                                                                                        Estimated    Actual
                                                                       Milestone
             The Safety Action Plan is aimed at preventing roadway                     Completion  Completion
             fatalities and serious injuries for all roadway users within   Issue Request for   Sept. 2023   Aug. 2023
             the City of Arlington. The Plan includes a safety analysis,   Qualifications
             robust public engagement, and a comprehensive list of   Select and Contract   Nov. 2023   Nov. 2023
             strategies and projects for implementation and will be   with Consultant
             completed in collaboration with the Arlington Police   Draft Plan         Sept. 2024   Sept. 2024
             Department and the Public Works Department. Funding   Final Plan          Oct. 2024
             for the Plan comes in part from a competitive Safe Streets
             and Roads for All grant awarded by the Federal Highway
             Administration to the City.

                       Federal Award      $240,000
                       Local Cash Match   $25,000
                       Local In-Kind Match   $102,984
                       Project Total      $367,984

             Update:
             In the 4th Quarter of FY 2024, safety projects were
             prioritized, common crash profiles were developed, a
             toolkit of actions and countermeasures to improve safety
             was developed, and the draft plan document was
             prepared. Community outreach continued, with meetings
             of the Internal Stakeholder Committee of City staff, one
             meeting of the External Stakeholder Committee of
             community representatives, and the third general public
             meeting. The project is on track for scheduled adoption of
             the plan by the end of 2024.