Page 293 - City of Watauga FY22 Adopted Budget
P. 293

CIP AND CAPITAL PROJECTS FUNDS




                   Operating Impact:  This street improvement will have little or no impact on operations.
                   It will be funded through developer fees, the 2018 Certificate of Obligation proceeds and
                   Storm Drain fees.

               ❖  Description:  Meadowlark Lane East – The
                   project  limits  of  Meadowlark Lane East  runs
                   from  Heather  Drive  to  west  of  Pebblebrook
                   Drive.    The  project  includes  a  complete
                   reconstruction  of  the  street,  water  main
                   improvements        and      sanitary     sewer
                   improvements. The new street section shall be
                   concrete  paving  with  4’  wide  sidewalks
                   running along both sides of the roadway.

                   Justification:  The existing asphalt pavement
                   in  Meadowlark  Lane  East  is  failing  and  the
                   sanitary  sewer  line  is  in  the  front  yards  of
                   people’s houses.  The project will relocate that sanitary sewer line to the street.

                   Operating Impact:  This street improvement is a continuation from last year and will be
                   completed in the spring of 2022.  The project will have little or no impact on operations.
                   It will be funded through the 2017 Certificate of Obligation proceeds.


                                         FY2021-2022 SIDEWALK PROGRAM

               ❖  Description:  Approximately 5,000 square feet of sidewalks will be maintained this fiscal
                   year.  The City identifies various sidewalks annually for replacement.

                   Justification:  Safe, pedestrian-friendly neighborhoods are a priority of our community.
                   An important component of this is the City’s Sidewalk Program which is developed to
                   provide for the maintenance of sidewalks within the City of Watauga.

                   Operating Impact:  The Sidewalk program this year is funded by  a transfer from the
                   General Fund to the General Capital Projects Fund.

                                 FY2021-2022 STORM DRAIN PROJECTS DISCUSSION

               ❖  Description:    The  Whitley  Road  Phases  1-6  projects  will  make  major  storm  drain
                   improvements along Whitley Road. Currently, there are ditches along Whitley Road that
                   carry the storm water. This storm water will be put under Whitley Road and carried by
                   pipes.










                                                             284