CIP AND CAPITAL PROJECTS FUNDS



                   Many have inflow and infiltration problems.  Proactive replacement, instead of reactive
                   replacement, will reduce maintenance costs and customer problems.

                   Operating  Impact:    Savings  of  approximately  $100,000  annually  are  expected  in
                   decreased wastewater fees paid due to prevention of inflow and infiltration into the system
                   after completion of this project.

                                 FY2021-2022 WATER PROJECTS DISCUSSION

               ❖  Description:  The continuation of the 2017 Water CIP will replace the aging 16” water
                   lines in Whitley Road and Starnes Road and various water lines throughout the city.  The
                   water  lines  are  old  and  present  frequent  maintenance  issues.    The  recommended
                   improvements will significantly increase the level of service of these water lines.  The
                   2019 Water CIP water line projects are planned for Derek Drive from Whitley Road to
                   Saramac Drive,  Melinda Drive from Jackie Terrace to Marigold Drive, MacArthur Drive
                   from Douglas Drive to Rebecca Lane and Hillcrest Drive from Quail Run to Echo Hill
                   Drive.