CIP AND CAPITAL PROJECTS FUNDS
System Evaluation Survey (SSES) was completed in FY2018-2019 in another section of
the city to identify additional high priority projects. Two separate projects will occur. The
first one will rehabilitate wastewater lines along the following streets: Hickoryhill Road
and Oakhill Road from Whitley Road to Maplehill Road; Echo Hill Drive from Hightower
Drive to Chapman Road; and Quail Run from Herschel Drive to Highcrest Drive. The
second project will rehabilitate wastewater lines along the following streets: Whispering
Lane from Wooddale Drive to Stardust Drive; Brookdale Drive from Hightower Drive to
Ridgecrest including Brookdale Court; Summit Ridge Drive from Rufe Snow Drive to
Avalon Drive including Summertime Lane; Oaklawn Drive from Mickey Drive to McCoy
Drive; Village Park Drive from Greendale Drive to Ridgetop Drive; and Watauga Road
from Patsy Lane to Morris Boulevard. The project will also rehabilitate and repair various
sanitary sewer manholes throughout the city.
Justification: The aging wastewater lines throughout the City are 30+ years old. The
lines are subject to ground movement, pulled joints, root infiltration and deterioration.