Page 295 - City of Watauga FY22 Adopted Budget
P. 295

CIP AND CAPITAL PROJECTS FUNDS



                   System Evaluation Survey (SSES) was completed in FY2018-2019 in another section of
                   the city to identify additional high priority projects.  Two separate projects will occur.  The
                   first one will rehabilitate wastewater lines along the following streets:  Hickoryhill Road
                   and Oakhill Road from Whitley Road to Maplehill Road; Echo Hill Drive from Hightower
                   Drive to Chapman Road; and Quail Run from Herschel Drive to Highcrest Drive.  The
                   second project will rehabilitate wastewater lines along the following streets: Whispering
                   Lane from Wooddale Drive to Stardust Drive; Brookdale Drive from Hightower Drive to
                   Ridgecrest  including  Brookdale  Court;  Summit  Ridge  Drive  from  Rufe  Snow  Drive  to
                   Avalon Drive including Summertime Lane; Oaklawn Drive from Mickey Drive to McCoy
                   Drive; Village Park Drive from Greendale Drive to Ridgetop Drive; and Watauga Road
                   from Patsy Lane to Morris Boulevard.  The project will also rehabilitate and repair various
                   sanitary sewer manholes throughout the city.






















































                   Justification:  The aging wastewater lines throughout the City are 30+ years old.  The
                   lines are subject to ground movement, pulled joints, root infiltration and deterioration.





                                                             286