Page 288 - City of Watauga FY22 Adopted Budget
P. 288

CIP AND CAPITAL PROJECTS FUNDS



            Watauga and continuation of the Green Ribbon Project which will beautify the 377 corridor.  A
            food  business  park  is  funded  by  the  Economic  Development  Corporation  to  spur  economic
            development.

            The following table shows the City’s 5-year Capital Improvement Projects Plan:

                                                                FUNDING
                                                                SOURCE   FY20-21 (CY) FY21-22  FY22-23  FY23-24  FY24-25  FY25-26
            REQUESTING DEPARTMENT PROJECTS  Location  Cost   FY2021-26   PROJECTED  BUDGET  FORECAST  FORECAST  FORECAST  FORECAST
                      PARKS                           $3,763,227          $1,755,227  $595,000  $503,000  $830,000  $80,000  $0
                      Material Bins - Parks Facility  Parks Facility Linda Drive  $30,000   2018 CO  $30,000
                      Dog Park          To Be Determined  $250,000   TBD - 2023 CO             $250,000
                      Pole Barn - Parks   Parks Facility Linda Drive  $65,000   2020 CO  $65,000
                      Capp Smith Weir   Capp Smith     $27,150   2018 CO    $27,150
                      Splashpad parking/sidewalks/drain  Capp Smith  $883,077   2016/2018 CO  $883,077
                      Whitesbranch Creek Trail  Park Vista  $300,000   2018 CO  $50,000  $250,000
                      Lighting Replacement   Capp Smith  $700,000   2018 CO  $700,000
                      Playground Equipment  Foster Village Park  $80,000   TBD 2022 CO   $80,000
                                        Hector Garcia  $80,000   TBD 2023 CO                    $80,000
                                        Hillview       $60,000   TBD 2023 CO                           $60,000
                                        Capp Smith Park  $20,000   TBD 2023 CO                         $20,000
                      Park Vista - Playground Project  Park Vista  $345,000   FUND WHEN DESIGN/ENG   $345,000
                                                                2018 CO
                      Foster Village Park Renovation - Eng  Foster Village Park  $180,000   REVENUES  $180,000
                      Trail Lights (Solar)  City-wide  $500,000   TBD 2023 CO                  $500,000
                      Site Amenities Improvements  City- wide - EDC  $43,000   TBD WITH EDC  $43,000
                      Retaining Wall Replacement  Capp Smith  $200,000  STORM DRAIN/TBD - 2022 CO  $200,000
                      BUILDING IMPROVEMENTS          $18,569,660           $969,660   $0    $0   $600,000   $0  $17,000,000
            Library   Library Roof Replacement  Whitley Road  $76,000   2020 CO  $76,000
                      Library Facility  To Be Determined   not in 5 year - 7 years out - Bond Election
                      Old Library - Renovation/convention  Whitley Road  not in 5 year - 7 years out
            Public Works  Fleet Bldg. Expansion  Virgil Anthony  $600,000   TBD 2023 CO        $600,000
            Public Safety - Police ACO Expansion-Renovation  Animal Control  $0   7 years out -Bond election
                      Police Facility Expansion/Rebuild  Whitley Road  $17,000,000   2023 Bond Election    $17,000,000
            Public Safety - Fire  Fire Station Restroom Renovation  Fire Station  $893,660   2020 CO  $893,660
                      Fire Station Design & Site Prep  Fire Station  2020 TAX NOTE
                      ECONOMIC DEVELOPMENT PROJECTS   $993,000             $193,550   $456,450   $343,000   $0   $0
            Econ.Development  Food Business Site  Capp Smith Park  $500,000   2020 CO  $43,550  $456,450
                                                          B
                                                         T
                      Pedestrian Bridge  Watauga Towne Crossing  $300,000 D WITH EDA GRANT or Tarrant County  $300,000
                      Branding Signs    City Wide      $150,000   2018 CO EDC   $150,000
                      Site Amenities Improvements  City- wide - EDC  $43,000   TBD WITH EDC  $43,000
            Public Works  DRAINAGE                   $14,034,590          $1,000,519  $2,937,111  $206,160  $1,889,800  $8,001,000
                      Whitley Rd. Ph. II (Drainage Portion)**  Watauga to Chapman  $200,000   Storm Drain  $200,000
                      Whitley Rd. Ph. III (Drainage Portion)** Chapman to Concord  $490,519   Storm Drain  $490,519
                      Whitley Rd. 4 (Drainage Portion)  Concord to Oakhill  $540,000   Storm Drain  $540,000
                      Pavestone Wall Repair  Capp Smith  $0    Storm Drain
                      Bunker Hill                     $2,027,111   Storm Drain   $2,027,111
                      Channel Protection/Ped. Rails  Multiple Locations  $150,000   Storm Drain  $150,000
                      Sunny Brook South               $7,801,000   TBD                                      $7,801,000
                      Astor Heights                   $2,095,960   Storm Drain           $206,160  $1,889,800
                      Blue Green Grey Project - Raingardens  Hightower  $90,000   ENG/GRANT FUNDING  $90,000
                      Park Vista Drainage/Ft. Worth  Park Vista  $200,000   Storm Drain                      $200,000
                      Drainage Master Plan             $440,000   Storm Drain  $220,000  $220,000
                      Future Storm Drain Projects        $0      TBD
            Public Works  STREET PROJECTS            $36,522,122          $2,019,948  $8,340,182  $10,203,992  $4,455,000  $5,010,000  $6,493,000
                      Chapman 1         Whitley to Brookdale  $3,643,000   2021/2022 CO & 1/2 TC  $442,000  $3,201,000
                      Chapman 2         Brookdale to Mona Lisa  $3,473,000   2022 CO & 1/2 TC  $440,000  $3,033,000
                      Chapman 3         Mona Lisa to Summit   $1,860,000   2023 CO & 1/2 TC    $242,000  $1,618,000
                      Chapman 4         Summit Ridge to Rufe   $1,871,000   2024 CO & 1/2 TC   $230,000  $1,641,000
                      Chapman 5                       $6,344,000   2024/2025 CO & 1/2 TC              $801,000  $5,543,000
                      Whitley Rd. Ph. III (Paving & Misc.)  Chapman to Concord  $1,755,920   2016 CO  $700,000  $1,055,920
                      Whitley Rd. 4     Concord to Oakhill  $2,709,262   2016 CO/2018 CO/2020 CO  $0  $2,709,262
                      Whitley Rd. 5     Starnes to North Tarrant  $6,395,992   2021, 2022 CO & TC  $783,000  $5,612,992
                      Signal Crossing - Hawk  Multiple Locations  $2,400,000   2021 CO & TC  $2,400,000
                      Bowie Street      377 to Plum    $419,948   2018 CO  $419,948
                      Green Ribbon Project (2-7)  377 Corridor  $250,000   ENG/GRANT FUNDING  $50,000  $50,000  $50,000  $50,000  $50,000
                      Sidewalks         Multiple Locations  $600,000   GF Revenues/CO funding  $100,000  $100,000  $100,000  $100,000  $100,000  $100,000
                      Overlays          Annual Determination  $4,800,000  Street Maint 2 YEARS/2018 CO  $800,000  $800,000  $800,000  $800,000  $800,000  $800,000
            Public Works  WATER & WASTEWATER PROJECTS  $19,182,297         $2,337,896  $6,885,201  $5,609,200  $50,000  $4,250,000  $50,000
                      CDBG Projects     TO BE DETERMINED  $650,000   CDBG/Rev  $0  $50,000  $250,000  $50,000  $250,000  $50,000
                      Whitley Rd. Ph. II (Water Portion)**  Watauga to Chapman  $186,500   2017 CO  $186,500
                      Whitley Rd. 4 (Water Portion)  Concord to Oakhill  $1,533,000   2017 CO  $0  $1,533,000
                      Meadowlark Lane East  Meadowlark  $1,706,387   2017 CO  $1,706,387
                      Group 1 W&S       Multiple Locations  $1,878,000   2019 CO  $1,126,800  $751,200
                      Group 2 W&S       Multiple Locations  $2,125,000   2019 CO  $255,000  $1,870,000
                      Group 3 W&S       Summertime    $1,583,410   2019 CO  $190,009  $1,393,401
                      Group 4 W&S       Multiple Locations  $1,520,000   2019 CO  $912,000  $608,000
                      Group 5 SSES      Multiple Locations  $0   2019 CO
                      Various Water and Sewer Projects  Multiple Locations  $4,000,000   TBD - 2022 CO  $4,000,000
                      Various Water and Sewer Projects  Multiple Locations  $4,000,000   TBD - 2024 CO  $4,000,000
                      Future Water/Wastewater  Multiple Locations  TBD
                                                     $93,064,896          $8,276,800  $19,213,944  $16,865,352  $7,824,800  $9,340,000  $31,544,000
                      MAINTENANCE W&S & STREETS       $1,440,000 W&S Rev/ST  $240,000  $240,000  $240,000  $240,000  $240,000  $240,000

                      GRAND TOTAL                    $94,504,896          $8,516,800  $19,453,944  $17,105,352  $8,064,800  $9,580,000  $31,784,000

                                                             279
   283   284   285   286   287   288   289   290   291   292   293