Page 499 - Southlake FY22 Budget
P. 499

CAPITAL IMPROVEMENTS  PROGRAM (CIP)

                                     FACILITIES



                                City of Southlake FY 2022 CIP Project Status Form

                                              Library and Multi-Use Facility

           DEPARTMENT: Public Works
           PROJECT
           LOCATION:   To Be Determined

           PROJECT TIMELINE: FY 2023  to  FY 2026
           DESCRIPTION:
           The purpose of this item is to establish a project fund for a combined library and
           multi-use facility. An up to 60,000 square foot building will be constructed with space
           for the library and space for multi-purpose uses.








                                                                    New Request     Continuation Project     Partnership
           JUSTIFICATION:                                           Mandated /    Replacement / Major   Community
                                                                    Public Health /      Rehab or Protection   Need / Service
           Facilities are inadequate and undersized for the current Library staff and patrons.  Safety  of Capital Stock  Enhancement
                                                                    2030/2035 COMPREHENSIVE PLAN? If yes, include ref:

                                                                    2030 Parks, Recreation & Open Space / Community Facilities
                                                                    Master Plan - Community Facilities Recommendation #2
           ALTERNATIVES / IMPACTS IF PROJECT IS NOT FUNDED:         COMPANION PROJECT? If yes, please explain:
           The current facility is undersized and unable to properly meet residents' expectations.  N/A
                                                                    REVENUE GENERATING? If yes, please explain:
           STRATEGIC FOCUS AREA: Infrastructure, Quality Development
                                                                    N/A
           PROJECT #:  2022-83
                                                    EXPENDITURE SCHEDULE
             CAPITAL PROJECT COSTS  TOTAL PRIOR  2022  2023    2024     2025     2026    UNFUNDED     TOTAL
              PLANNING / FEASIBILITY STUDY  62,700                                                   62,700
             ENGINEERING & DESIGN; TESTING          2,500,000                                       2,500,000
                 LAND & ROW ACQUISITION                                                                0
           LANDSCAPING,  ART,  URBAN  DESIGN                22,200,000  4,500,000  1,237,300        27,937,300
                      CONSTRUCTION                           2,125,000  375,000                     2,500,000
                       CONTINGENCY                                                                     0
                          TOTAL   62,700     0      2,500,000  24,325,000  4,875,000  1,237,300  0  33,000,000
                                                     OPERATIONAL IMPACT
           OPERATIONAL PROJECT COSTS  TOTAL PRIOR  2022  2023  2024     2025     2026    UNFUNDED     TOTAL
                   MAINTENANCE COSTS                                   40,000   80,000               120,000
                    PERSONNEL COSTS                                             400,000              400,000
                          TOTAL    0         0        0        0       40,000   480,000     0        520,000
                                                      FUNDING SCHEDULE
             CAPITAL FUNDING SOURCE  TOTAL PRIOR  2022  2023   2024     2025     2026    UNFUNDED     TOTAL
                      GENERAL FUND  450,000  0      3,000,000  8,000,000  6,550,000  15,000,000  0  33,000,000
                           CEDC                                                                        0
                           CCPD                                                                        0
               PARK DEDICATION FEE FUND                                                                0
                     PUBLIC ART FUND                                                                   0
               ROADWAY IMPACT FEE FUND                                                                 0
              SANITARY SEWER IMPACT FEE                                                                0
                           SPDC                                                                        0
           STORMWATER UTILITY SYSTEM FUND                                                              0
                          TIRZ #1                                                                      0
                       UTILITY FUND                                                                    0
                 WATER IMPACT FEE FUND                                                                 0
                          TOTAL  450,000     0      3,000,000  8,000,000  6,550,000  15,000,000  0  33,000,000
           CCPD: CRIME CONTROL & PREVENTION DISTRICT                                SPDC: SOUTHLAKE PARKS DEVELOPMENT CORPORATION
             CEDC: COMMUNITY ENHANCEMENT & DEVELOPMENT CORPORATION                     TIRZ #1:  TAX INCREMENT REINVESTMENT ZONE #1

      498   FY 2022 City of Southlake  |  BUDGET BOOK
            WWW.CITYOFSOUTHLAKE.COM