Enhance Regional Mobility Scorecard
FY 2019 FY 2020 FY 2021 FY 2022
Dept. Key Measures
Actual Actual Estimate Target
PWT Citizen perception of overall condition of
streets/roads as "excellent" or "good" [annual Maintain or
survey] 40% 44% 46% Increase
PWT Citizen perception of traffic levels are
acceptable as "strongly agree" or "somewhat Maintain or
Citizen Survey agree" [annual survey] 39% 39% 48% Increase
PWT Citizen perception of excellent or good for Maintain or
traffic flow management in the
Entertainment District [annual survey] 37% 41% 47% Increase
PWT Citizen perception of overall satisfaction with
the management of traffic flow during peak
hours as "excellent" or "good" [annual Maintain or
survey] 39% 39% 47% Increase
OSI Via On‐Demand Rideshare Ridership 233,717 179,995 195,000 300,000
PWT Travel time on northbound Cooper from
Turner‐Warnell to I‐30 (goal: 21 min 9 sec) 21:09 (+/‐ 2
[measured quarterly] 21:54 20:54 20:43 min 7 sec)
PWT Travel time on southbound Cooper from I‐30
to Turner‐Warnell (goal: 21 min 4 sec) 21:04 (+/‐ 2
[measured quarterly] 21:49 21:50 19:24 min 6 sec)
PWT Travel time on northbound Collins from South
Green Oaks to North Green Oaks (goal: 19 19:38 (+/‐ 1
min 38 sec) [measured quarterly] 19:42 20:44 19:31 min 58 sec)
PWT Travel time on southbound Collins from North
Green Oaks to South Green Oaks (goal: 19 19:34 (+/‐ 1
min 34 sec) [measured quarterly] 18:27 19:45 18:04 min 57 sec)
PWT Travel time on eastbound Division from 10:24 (+/‐ 1
Bowen to SH‐360 (goal: 10 min 24 sec)
Traffic Management 360 to Bowen (goal: 10 min 52 sec) 10:52 (+/‐ 1
PWT [measured quarterly] 11:36 11:00 10:44 min 2 sec)
Travel time on westbound Division from SH‐
PWT [measured quarterly] 11:21 8:17 9:30 min 5 sec)
Travel time on eastbound Pioneer Parkway
from Green Oaks to SH‐360 (goal: 13 min 49 13:49 (+/‐ 1
sec) [measured quarterly] 13:49 13:49 12:41 min 23 sec)
PWT Travel time on westbound Pioneer Parkway
from SH‐360 to Green Oaks (goal 14 min 12 14:12 (+/‐ 1
sec) [measured quarterly] 13:40 14:04 12:45 min 25 sec)
PWT Lane Miles with Overall Condition Index (OCI) Maintain or
< 50 [measured quarterly] 300 347 377 Decrease
PWT % of traffic signals receiving annual
preventative maintenance compared to goal
of 535 [measured quarterly] 100% 99% 52% 100%
PWT % of signs replaced that do not meet
minimum standards compared to annual goal
of 3,000 112% 95% 100% 100%