                                           Enhance Regional Mobility

                          Goal 2: Plan, Manage, and Maintain Public Transportation Infrastructure
                           Objective 1: Optimize Effectiveness and Efficiency of Existing Transportation System
                          Project                   Performance Measure(s)                Department(s)
             ERM   Thoroughfare Development   Completion of Update              Office of Strategic Initiatives
             2.1.4  Plan Update
             Summary:
                                                                     Milestone         Estimated      Actual
             The Thoroughfare Development Plan (TDP) is a long‐                        Completion   Completion
             range plan that identifies the location and types of   Issue Request for   Nov. 2021   In Progress
             roadway facilities that are needed to meet projected   Qualifications
             long‐term growth within the City of Arlington. The   Select and Contract with   Jan. 2022
             project will use an updated travel demand model to re‐  Consultant
             evaluate street classifications and cross sections and   Draft Update     Sept. 2022
             update the Thoroughfare Development Plan map. The   Final Update          Nov.  2022
             project will also include a detailed traffic analysis of two

             specific areas: The Mesquite Street/Center Street one‐
             way pair and the section of Matlock Road between
             Pioneer Parkway and Cooper Street.