Enhance Regional Mobility
Goal 2: Plan, Manage, and Maintain Public Transportation Infrastructure
Objective 2: Complete Construction Projects in a Timely Manner
Project Performance Measure(s) City Service Team (Department)
ERM Street Rebuild Projects Overall satisfaction with the Public Works & Transportation
2.2.1 management of traffic flow during
peak hours
Summary:
Roadway Capital Improvements Project Lane
Capital street projects are funded with Street Bonds Miles
and are funded through inclusion in the annual capital 2018 Residential Rebuild (Daniel Dr.) 1.5
budget. 2018 Residential Rebuild (Miriam Ln.) 1.4
2019 Residential Rebuild 0.8
The projects listed to the right are expected to receive 2020 CDBG Vanderbilt Dr. & Hanover Dr. 1.2
construction funds in March 2021. The projects listed Avenue E (SH‐360 to Great Southwest Pkwy.) 4.0
below include carry‐over projects funded in prior years Avenue H (SH‐360 to Great Southwest Pkwy.) 4.6
that have not completed construction, as well as the
Bowman Springs Road (IH‐20 to Enchanted Bay 1.1
planned FY 2021 projects. Project milestones listed in
Blvd.)
the table will be updated as they occur during the year. Calender Road (Harris Rd. to Eden Rd.) 1.4
Eden Road (US‐287 to Calender Rd.) 2.0
Harris Road (Calender Rd. to Cooper St.) 2.2
Poly Webb Road (Pleasant Ridge Rd. to
Shorewood Dr.)
Sublett Road (City Limits to Joplin Rd.) 1.2
Turner Warnell Road (Matlock Rd. to Cooper St.) 6.0
Roadway Capital Improvement Project Estimated Actual Bid Estimated Actual
Bid Date Date Completion Completion
Eden Road (US‐287 to Calender Rd.) June 2018 Aug. 2019 July 2021 Sept. 2021
Calender Road (Harris Rd. to Eden Rd.) Apr. 2019 May 2020 Nov. 2021
Avenue H (SH‐360 to Great Southwest Pkwy.) May 2019 Sept. 2019 June 2021
Harris Road (Calender Rd. to Cooper St.) May 2019 Nov. 2020 Oct. 2022
2018 Residential Rebuild (Daniel Dr.) May 2020 Oct. 2020 Aug. 2021
2018 Residential Rebuild (Miriam Ln.) Oct. 2020 Oct. 2020 Nov. 2021
2020 CDBG Rebuilds (Vanderbilt Dr. & Hanover Dr.) July 2020 Sept. 2020 Dec. 2021
Avenue E (SH‐360 to Great Southwest Pkwy.) Aug. 2020 Nov. 2020 July 2022
2019 Residential Rebuild Apr. 2021 Apr. 2021 Feb. 2022
Poly Webb Road (Pleasant Ridge Rd. to Shorewood Oct. 2021
Dr.)
Turner Warnell Road (Matlock Rd. to Cooper St.) Oct. 2021
Bowman Springs Road (IH‐20 to Enchanted Bay Blvd.) Nov. 2021
Sublett Road (City Limits to Joplin Rd.) Nov. 2021