Goal 1: Plan, Manage, and Maintain Public Assets
Objective 2: Maintain City Standards for all Municipal Buildings
Project Performance Measure(s) Department(s)
Core Fire Station #1 Rebuild Overall satisfaction of project Asset Management and Fire
INF management
1.2.1 Project completion on time and at
budget
Summary:
In November 2014, Arlington voters approved Estimated Actual
general obligation bonds for the reconstruction of Milestone Completion Completion
Fire Station #1. The Arlington Fire Department has Initial Project Dec. 2018 Dec. 2018
partnered with Asset Management to re‐design the schedule/development phase
existing facility located at 401 W. Main St. The station Architect/engineer RFQ Oct. 2019 Oct. 2019
is at the heart of the City’s Downtown and one of the Architect/engineer selection Nov. 2019 Dec. 2019
oldest facilities currently managed by the Fire process
Department and was most recently remodeled in Architect/Engineer contract Dec. 2019 Jan. 2019
1987.
approval and execution
Manager at Risk contract Dec. 2019 Jan. 2020
approval and execution
Construction Management at Fall 2020 Feb. 2020
Risk process
Design Sept. 2021 July 2021
Guaranteed Maximum Price to Sept. 2021 Aug. 2021
Council
Permit review process Aug. 2021
Council approval Sept. 2021 Aug. 2021
Vacate station Sept. 2021
Demolition phase Dec. 2021
Construction phase Dec. 2021
Move in Dec. 2022