Goal 1: Plan, Manage, and Maintain Public Assets
Objective 2: Maintain City Standards for all Municipal Buildings
Project Performance Measure(s) Department(s)
Core Police Evidence Storage, Crime Overall Satisfaction of Project Asset Management and Police
INF Lab & North District Management
1.2.2 Substation Project Completion on Time and
at Budget
Summary:
In November 2018, Arlington voters approved Milestone Estimated Actual
general obligation bonds to design and build a new Completion Completion
Police Evidence Storage Facility. In Winter of 2021, Initial Project May 2021
City Council approved the purchase of a commercial Schedule/Development Phase
property at 1715 E. Lamar Blvd. This property will be Request for Qualifications for June 2021
converted into a new facility for the Police Architect/Engineer
Department that will house a North District Architect/Engineer Selection Sept. 2021
substation, evidence storage and crime lab. Process
Council Approval of Architect Oct. 2021
Contract
Design Phase Nov. 2021
Finalize Construction Documents Jan. 2022
Permit Phase Jan. 2022
Bidding Phase Mar. 2022
Construction Begins Dec. 2022
Finalize Selection of Fixtures, Sept. 2023
Furniture, and Equipment
Construction Complete Jan. 2023