Project Performance Measure(s) Department(s)
Core Active Adult Center Overall satisfaction of project management Asset Management and Parks &
CRE Project completion on time and at budget Recreation
1.1.2 Citizen satisfaction with overall quality of
parks and recreation programs and classes
Summary:
In a special election on May 6, 2017, Arlington Milestone Estimated Actual
voters approved obligation bonds to build an Active Completion Completion
Adult Center. This new facility for residents 50 years Initial Project Jan. 2019 Jan. 2019
of age and older will be located on the southwest Schedule/Development Phase
corner of the Pierce Burch Water Treatment site on Architect/Engineer RFQ July 2019 July 2019
Green Oaks Boulevard between W. Arkansas Lane Architect/Engineer RFQ July 2019 July 2019
and W. Pioneer Parkway. Architect/Engineer Selection Oct. 2019 Dec. 2019
Process
In April 2019, the City investigated alternative Council Approval of Architect Dec. 2019 Mar. 2020
construction delivery methods for the project. A
Contract
determination was made to proceed with a Request
CMAR approved delivery Fall 2021 Jan. 2020
for Qualifications (RFQ) for a Construction Manager method to Council
at Risk. However, with the onset of the COVID‐19 Finalize construction Spring 2022
pandemic, this RFQ was ultimately canceled. documents
Permit Process Spring 2022
In July 2019, the City issued an RFQ for Guaranteed Maximum Price to Spring 2022
Architectural/Engineering firms to design the new Council
facility. Parkhill, Scott and Cooper were selected as Construction begins Summer 2022
the A/E firm for the project and began verification
of the project program. Finalize selection of furniture Fall 2023
and equipment
Construction complete Winter 2024