Page 410 - NRH FY20 Approved Budget
P. 410

Utility Capital Projects



           Project Name                                      Project Description
         Garwood Drive Sanitary Sewer   This is the 45th Year Community Development Block Grant (CDBG) Project.  The project will consist of reconstructing
         (CDBG) - New Project   approximately 1,400 linear feet of sanitary sewer main.









         Johnson Pump Station   This project will consist of the replacement of (2) two pumps and motors inside the Johnson Pump Station facility
         Component and Infrastructure   located at 8501 Harwood Road.  Included will be replacement of a short section of discharge header pipe outside the
         Replacements - Continuing   pump station, replacement of the entry pipe from the road side to the storage tank, and replacement of the manually
         Project                operated water valve with a motorized valve on the entry pipe.







         Large Valve Replacement   The Large Water Valve Replacement Project encompassed the replacement of two, 24 inch valves, a 12 inch valve, and
         Project - Continuing Project  the installation of a 16 inch valve.  The 24 inch valve replacements are located at the intersections of Hightower and
                                Smithfield Road and Hightower and Davis Boulevard.  The 12 inch valve replacement is located at Davis Boulevard and
                                Odell Street.  The installation of the 16 inch valve will be near the intersection of Glenview Drive and Dawn Drive.







         Main / Snider / Center Utility   The project consists of engineering and construction of water and sanitary sewer main extensions to provide service to
         Project - Continuing Project  properties north and south of Main Street off of Snider Street and Center Street in the TOD.









         Miscellaneous Water/Sewer   This is an annual program that is completed by the Public Works Construction Division (407-6007).  The program will
         Main Replacement (2019) -   provide for water and sewer main replacements including any developmental projects.  The project replaces aging
         Continuing Project     infrastructure and maintains high standards for water quality.  This will include replacements on the following streets:
                                Whitfield Court (Holiday to Culd-de-sac), Lariat Trail (Meadowridge to Meadow Lakes), Southampton Drive ( Wakefield
                                to Chapman), and Holiday Court (Green Meadows to Cul-de-sac).






         Miscellaneous Water/Sewer   This is an annual program that is completed by the Public Works Construction Division. The program will provide for
         Main Replacement (2020) - New   water and sewer main replacements including any developmental projects. The project replaces aging infrastructure and
         Project                maintains high standards for water quality. This will include replacements on the following streets: Oldham Place
                                (Buckingham Trail - Yarmouth Avenue), Shadydale Drive (Meadowview Ter. - Crosstimbers Lane), Southampton Road
                                (Chapman Road - Wakefield Road) and Susan Court (Scott Drive - 7533 Susan Court).