           Project Name                                      Project Description
         Northfield Park Renovation -   This project involves the redevelopment of the existing community park through the design and construction of new
         Continuing Project     amenities based on meetings to gather stakeholder input. Recommended park elements for the redevelopment of the
                                park include a new park entry, a more efficient park layout, upgrade of all equipment and support facilities and
                                introduction of loop trails. The project will also ensure the protection of the natural creek corridor and provide engaging
                                views to natural areas.






         NRH Centre Indoor Aquatic Pool   This project is to re-plaster the Aquatics Facility at the NRH Centre.  The pool plaster serves as a waterproof layer
         Re-Plaster - Continuing Project  between the pool water and the shell of the pool, protecting it's structural integrity.  The project will include removal and
                                replacement of all the pool plaster down to the substrate/gunite surface. Specifications of the project will include needed
                                substrate repairs, tile repair and replacement of grates as needed.  In order to provide the most minimal impact to the
                                NRH Centre public operations this project is expected to be completed within the month of December 2018 so that the
                                facility can re-open to the public on January 1, 2019.  This project was initially budgeted in the FY 2017-18 NRH Centre
                                Operating Budget. Staff obtained estimates from local pool vendors, however the formal bids significantly exceeded the
                                available budget.  All bids were rejected and only patch repairs have been completed to date.


         Park Infrastructure Maintenance   This project provides for maintenance of park infrastructure in response to use and age. The FY2020 priorities include
         (2020) - New Project   Fall Zone Material, Concrete Trail Panel Replacement, Playground Equipment Replacement, Sport Field Bulb
                                Replacement, Sports Field Infield Refurbishment, Drinking Fountain Replacement, Green Valley Arch and Soffit Repair
                                and Replacement, Liberty Park Granite Plaque, Norich Park Drainage, Ace Park Fence Replacement, Norich Park
                                Fence Repair, Green Valley Drainage Infrastructure Study, Walkers Creek Park Dumpster and Northfield Park
                                Bleachers.





         Park Infrastructure Maintenance   This Project provides for maintenance of park infrastructure in response to use and age. The Parks and Recreation
         2015 - Continuing Project  Department developed an Infrastructure Management Plan for park amenities. The plan addresses the long term
                                funding needs for replacement and renovation of park sites and their amenities, demonstrating responsible stewardship
                                of property assets by the City. Funding is included to address sports field renovation, sidewalk and trail repair, bridge
                                deck replacement, replacement of park furniture and drinking fountains, park rules and regulation sign replacement and
                                irrigation renovation.





         Park Infrastructure Maintenance   This project provides for maintenance of park infrastructure in response to use and age. The FY 2017-2018 priorities
         2018 - Continuing Project  include concrete trail repair, retaining wall repairs, park restroom partitions and fixtures, athletic field fencing, erosion
                                control, playground fall zone material, security lighting maintenance, restroom/concession building repairs and drinking
                                fountain repairs and replacement.







         Park Infrastructure Maintenance   This project provides for maintenance of park infrastructure in response to use and age. The FY2019 priorities include
         2019 - Continuing Project  Playground Equipment Replacement, Fall Zone Material, Drinking Fountain Replacement, Sport Field Bulb
                                Replacement, Liberty Park Paver Repairs, Richfield and Green Valley AC Replacement, Fossil Creek Restroom
                                Removal, Trail Ramp Concrete Stain, Cross Timbers Dugout Roofs, Sports Field Infield Refurbishment, Green Valley
                                Dumpster Fence, Adventure World Fence Replacement, Ballfield Fence Replacement.