Page 426 - City of Bedford FY20 Approved Budget
P. 426

CITY OF BEDFORD
                                                   MAJOR FACILITY MAINTENANCE
                                                           FY 2019-2020

               Funding Sources:
               (1) General Obligation Bonds  (4) Street Improvement E.D.C.  (10) PPF Contractual Obligation
               (2) Certificates of Obligation  (5) Water & Sewer Utility Repair Fund  (11) Cash
               (3) Revenue Bonds  (6) Equipment Replacement Fund  (TBD) To Be Determined
                                             TOTAL EST. CURRENTLY                                          FUNDING
               PROJECT                         COST   FUNDED  FY 18/19  FY 19/20  FY 20/21  FY 21/22  FY 22/23  FY 23/24  SOURCE
               GENERAL GOVERNMENT
               IT Infrastructure at Former Library  17,000  No  17,000                                       TBD
               Ramps and Sidewalk on L Don Dodson  10,000  Yes  10,000                                        11
               HVAC Replacement - Former Library  69,900  No   69,900                                        TBD
               LED Lighting Project               TBD   No                       TBD                         TBD
               Replacement of City Hall Generator & Electrical Work  400,000  No  400,000                    TBD
               HVAC Replacement City Hall A & B  64,500  No                     64,500                       TBD
               City Hall A Roof Replacement      146,500  No                    146,500                      TBD
               City Hall B Roof Reeplacement     89,900  No                     89,900                       TBD
               Old Library Roof Replacement      163,250  No                    163,250                      TBD
               POLICE
               Law Enforcement Center Roof Replacement  1,000,000  No          1,000,000                     TBD
               Animal Control Roof Replacement   37,225  No                     37,225                       TBD
               Perimeter Fence & Gate            235,000  No                    235,000                      TBD
               Protective Awning for Police Department Vehicles  60,000  No     60,000                       TBD
               Camera System                     77,000  No                     77,000                       TBD
               Electronic Monument Sign          20,000  No                     20,000                       TBD
               Paint Law Enforcement Center Building  8,000  No                  8,000                       TBD
               FIRE
               Carpet Replacement - All Stations  29,000  Yes    5,000   6,000   8,000  10,000                11
               Painting - All Stations           20,000  Yes            10,000   5,000   5,000                11
               HVAC Replacement - Fire Station 1  72,600  No            72,600                               TBD
               Station 3 Drive Improvements      55,000  No             55,000                               TBD
               Security Camera System            60,000  No                     20,000  20,000  20,000       TBD
               8' Concrete Screening Wall Station 1  300,000  No                       300,000               TBD
               8' Concrete Screening Wall Station 2  75,000  No                         75,000               TBD
               8' Concrete Screening Wall Station 3  100,000  No                       100,000               TBD
               PUBLIC WORKS
               Service Center Bathroom Rehabilitation  125,000  Yes  125,000                                  11
               Service Center Flooring Replacement  20,000  Yes  20,000                                       11
               HVAC Replacement Service Center   51,900  Yes     51,900                                       11
               Service Center Bay Doors Replacement  24,000  No         24,000                               TBD
               Fleet Floor Resurfacing           100,000  No            100,000                              TBD
               Flooring Replacement in Fleet shop offices  8,000  No     8,000                               TBD
               Front Entrance ADA Compliant       TBD   No               TBD                                 TBD
               LED lighting in Fleet shop         TBD   No                       TBD                         TBD
               Service Center front door automatic opener  TBD  No               TBD                         TBD
               Service Center Mud/Water Sand Trap Separator   190,000  No       190,000                      TBD
               HVAC System for Garage            80,000  No                     80,000                       TBD
               COMMUNITY SERVICES
               Library Teen Room Carpet Replacement  11,000  Yes        11,000                                11
               Library Red & Light Green Carpet Replacement  13,500  Yes  13,500                              11
               Automated Sprinkler System        100,000  No                    50,000  50,000               TBD
               Library Carpet Replacement        45,000  No                                     45,000       TBD
               TOTALS                          $3,833,275      $298,800  $300,100  $2,654,375  $560,000  $65,000  $0

























                                                             393
   421   422   423   424   425   426   427   428   429   430   431