Summary:
Milestone Target Date Status
The project is to upgrade to the AMANDA 7 version. Planning Phase Apr. 2017 Complete
This will keep the AMANDA Software on the current Create New AMANDA7 May 2017 Complete
Application Roadmap thereby continuing to maintain Environment
vendor application support while providing new Migrate all AMANDA6 July 2017 Complete
capabilities and functionality. objects to AMANDA7
User Training Aug. 2017 Complete
The project includes the following milestones: User Testing & Acceptance Dec. 2017 Complete
Create new AMANDA 7 environment Go‐Live on AMANDA7 Jan. 2018 Complete
Convert all AMANDA 6 objects to AMANDA 7 Create new AMANDA7 Test Jan. 2018 Complete
including the Public Portal environment
Convert and import data into AMANDA 7 Project Close Feb. 2018 Complete
environment
Conduct User Testing and Training
Start user AMANDA 7 (Go Live)
The project is planned to close in 2018.
Update:
This project is complete.