Page 374 - City of Arlington FY19 Adopted Operating Budget
P. 374

Put Technology to Work


                           Goal 1: Ensure Availability of Information, Programs, and City Services
                        Objective 1: Provide for the Efficient Access and Appropriate Management of the City’s Data
                            Project                 Performance Measure(s)       City Service Team (Department)
             PTW   Data Analytics Phase II, City Data   Project Completion   Strategic Support (IT) and Economic
             1.1.1  Strategic Plan                                          Development and Capital Investment (CDP)
             Summary:
                                                                      Milestone          Target Date    Status
             This project will utilize Esri software and Esri Enterprise   Phase II Project Kickoff   Oct. 2017   Complete
             Advantage Program services to support the City Data   Esri Architecture Design   Dec. 2017   Complete
             Strategic Plan by achieving:                      Architecture              Dec. 2017    Complete
                   Big data integration and management        Implementation/ ArcGIS
                   Data analytics capabilities                Enterprise Jumpstart
                   Enhanced Open Data capabilities            ArcGIS GeoEvent Server    2  Qtr. 2018   Complete
                                                                                          nd
                                                               Portal Template           2  Qtr. 2018   Complete
                                                                                          nd
             Deliverables include:                             Configuration
                   Geographic Information System (GIS) IT     ArcGIS Monitor Workshop   2  Qtr. 2018   Cancelled
                                                                                          nd
                    architecture design and implementation     Training                  3  Qtr. 2018   Complete
                                                                                          rd
                   Web applications providing useful information   Quick Hits – Design / Build    4  Qtr. 2018   In
                                                                                          th
                    to the public                                                                     Progress
                   Real time 2‐way data communication through   Phase II Project Kickoff   4  Qtr. 2018   Cancelled
                                                                                          th
                    GeoEvent Server
                   Data visualization utilizing the Insights product

             Update:
                   th
             In the 4  Quarter, Data Analytics upgraded ArcGIS   Note:
                                       th
             Enterprise to 10.6 on July 19‐20 .              1.  ArcGIS Monitor Workshop Cancelled – System upgrades
                                                                 providing Operations Dashboard in Insights were
             Virtual Maps was upgraded and placed in production   prioritized higher than the ArcGIS Monitor Workshop.
             Oct. 2, 2018.                                   2.  Quick Hits – Design /Build – Quick Hits included
                                                                 applications for Neighborhood Amenities, Food
             The Entertainment District Road Closure application has   Establishment Inspection, and Road Closure.  The
             been developed for traffic engineers to provide event   Entertainment District Road Closure application is being
             road closures to Waze. The application is currently   tested for planned go live Nov. 9, 2018.
             available to Traffic Engineering for testing.   3.  Phase III Project Kickoff 4  Quarter ‐ Funding for
                                                                                     th
                                                                 continuing the EEAP in 2019 was not approved.  The
             A Vector Bourne Illness Application has been developed   credits remaining from the 2018 program have been
             and is available for field testing.                 allocated to be used by Dec. 31, 2018

             The EEAP program ended Sept. 31. 2018.  The remaining
             credits have been allocated to:
                    GeoEvent Administration Consulting
                    Performance Management Solution Consulting
                    ArcGIS Enterprise Data Integration Consulting
                    General Consulting Support
                    ArcGIS Enterprise Admin Training

             Credits are to be used by Dec. 31, 2018.