Drainage - Sulphur Branch Tributary Culvert Improvements at
Bridges (Briar Drive, Shirley Way, Circle Lane, Schumac Lane, and
Donna Lane)
Overview
Joe Schweizer, Director of Public Works
Request Owner
06/01/2027
Est. Start Date
09/30/2027
Est. Completion Date
Public Works
Department
Capital Improvement
Type
Description
Culvert improvements at bridge headwalls on Briar Drive, Shirley Way, Circle Lane, Schumac Lane, and Donna Lane.
Briar - Design ($35,000 in FY 27), Construction ($260,000 in FY 29);
Shirley - Design ($40,000 in FY 28), Construction ($320,000 in FY 30)
Circle Lane, Schumac Lane, and Donna Lane TBD.