            Drainage - Erosion Control Sulphur Branch & Sulphur Branch
            Tributary, Second Phase of Brookhollow Park



            Overview
                                               Joe Schweizer, Director of Public Works
            Request Owner
                                               10/01/2027
            Est. Start Date
                                               09/30/2030
            Est. Completion Date
                                               Public Works
            Department
                                               Capital Improvement
            Type

            Description
            A section of the concrete channel wall adjacent to Brookhollow Park, from Rankin Drive to the pedestrian bridge, collapsed in February
            2018 during heavy rainstorms. Various other sections were also compromised. The project consists of the reconstruction of approximately
            400 linear feet of an existing channel.





            Details
                                               Stormwater Infrastructure Improvement
            Project Type