Page 417 - CityofArlingtonFY26AdoptedBudget
P. 417

Public Safety

                 Goal 1: Utilize Targeted Initiatives and Industry Best Practices and Policies to Foster a Safe
                                                        Environment
                                           Objective 1: Improve Quality of Life and Place
                          Project                   Performance Measure(s)                Department(s)
             Core   Arlington Fire Department   Overall satisfaction of project   Fire and Asset Management
             PS     Fire Station Location Study   management
             1.1.11
             Summary:
                                                                                          Estimated    Actual
                                                                       Milestone
             The placement of fire stations has a dramatic impact on                     Completion  Completion
             the effectiveness and efficiency of services provided by any   Inventory Existing Fire   Aug. 2024   Already
             fire department. Station location analysis begins with an   Stations                    existed in
             evaluation of the distribution of apparatus and personnel                               current
             throughout a department’s service area relative to                                      GIS
             demand for the department’s services and the ability to   Determine Service Areas   Dec. 2024   6/13/24
             meet. We will use geospatial and statistical analysis   and Response Modeling           off CAD
             modeling, input from stakeholders, and continual research                               data and
             into where we are not meeting standards for NFPA 1710.                                  7/2/24
                                                                                                     included
             Update:                                                                                 RMS data
                          rd
             No update for 3  Quarter FY 2025.                  Identify Properties that   Dec. 2024   8/9/24
                                                                can be purchased or used
                                                                for future fire stations
                                                                City GIS team compiled   Dec. 2024   8/9/24
                                                                date to create Scorecard
                                                                for ½ mile grid areas.
                                                                Presentation to the     Jan. 2025    01/24/25
                                                                Arlington Fire Association
                                                                showing 2015 W Mayfield
                                                                as primary location choice
                                                                for Station 18
                                                                Using Deccan ADAM       09/2025
                                                                Module and COA GIS to
                                                                determine locations 5, 10,
                                                                15 year projection