Page 417 - CityofArlingtonFY26AdoptedBudget
P. 417
Public Safety
Goal 1: Utilize Targeted Initiatives and Industry Best Practices and Policies to Foster a Safe
Environment
Objective 1: Improve Quality of Life and Place
Project Performance Measure(s) Department(s)
Core Arlington Fire Department Overall satisfaction of project Fire and Asset Management
PS Fire Station Location Study management
1.1.11
Summary:
Estimated Actual
Milestone
The placement of fire stations has a dramatic impact on Completion Completion
the effectiveness and efficiency of services provided by any Inventory Existing Fire Aug. 2024 Already
fire department. Station location analysis begins with an Stations existed in
evaluation of the distribution of apparatus and personnel current
throughout a department’s service area relative to GIS
demand for the department’s services and the ability to Determine Service Areas Dec. 2024 6/13/24
meet. We will use geospatial and statistical analysis and Response Modeling off CAD
modeling, input from stakeholders, and continual research data and
into where we are not meeting standards for NFPA 1710. 7/2/24
included
Update: RMS data
rd
No update for 3 Quarter FY 2025. Identify Properties that Dec. 2024 8/9/24
can be purchased or used
for future fire stations
City GIS team compiled Dec. 2024 8/9/24
date to create Scorecard
for ½ mile grid areas.
Presentation to the Jan. 2025 01/24/25
Arlington Fire Association
showing 2015 W Mayfield
as primary location choice
for Station 18
Using Deccan ADAM 09/2025
Module and COA GIS to
determine locations 5, 10,
15 year projection
123