Page 421 - CityofArlingtonFY26AdoptedBudget
P. 421
Public Safety
Goal 2: Mitigate Flood Risks and Protect Stormwater Infrastructure
Objective 1: Plan and Implement Stormwater Projects
Project Performance Measure(s) Department(s)
Core Stormwater Projects Implement Projects That Mitigate Public Works
PS Flooding Concerns
2.1.1
Summary:
Harvest Hills Channel now has all necessary easements
Stormwater Projects are funded through the Stormwater acquired. Negotiations for relocation of Oncor facilities in
Utility Fee and are included in the annual capital budget as conflict with the proposed channel are ongoing. FEMA
well as in the Comprehensive Stormwater Master Plan. review for the project is ongoing.
Update:
The Miscellaneous Stormwater Construction contract will
continue until all funds are used. There are no projects in
active construction. The California Lane Phase 1 is
complete, they are pouring the remaining manhole tops.
Construction is ongoing in the Fox Hill. area. California
Lane Phase 2 is in design, waiting for Alternative Analysis
Submittal from the consultant.
The projects listed below include major maintenance projects that began construction prior to FY 2025 as well as the
planned FY 2025 construction projects. Project milestones listed in the table will be updated as they occur.
Linear Feet of
Stormwater Capital Est. Bid Actual Bid Estimated Actual
Improvement Project Date Date Completion Completion Pipes/Channels
Constructed
2023 Miscellaneous Stormwater Oct. 2023 Oct. 2023 Jan. 2025 1,950 LF of Pipe, 250 LF
Construction of Channel
Lower Johnson Maintenance Mar. 2024 Mar. 2024 Feb. 2025 Mar. 2025 NA
Ramp and Erosion
Lower Johnson Creek Dredging, May 2024 May 2024 Feb. 2025 Mar.2025 NA
Phase 2
The projects listed below include major flood mitigation projects that began construction prior to FY 2025 as well as the
planned FY 2025 construction projects. Project milestones listed in the table will be updated as they occur.
Linear Feet of
Stormwater Capital Structures Est. Bid Actual Bid Estimated Actual
Pipes/Channels
Improvement Project Protected Date Date Completion Completion
Constructed
California Ln. Drainage 60 (all June 2022 Feb. 2023 Aug. 2025 June 2025 7,814 LF of Pipe
Improvements Phase 1 phases)
Harvest Hills Drainage 47 (all Aug. 2019
Improvements Phase 1 phases)
127