Business Plan




                                               Grow Our Economy

                                            Forge Local Business Community
                          Project                   Performance Measure(s)                Department(s)
             Ben Thanh Plaza Improvement Project   • Recruitment Leads          Economic Development Services and
                                               • Leads to Prospects             Economic Development Corporation

             Summary:                                                                                Percent
             Ben Thanh Plaza will soon see several enhancements,    Milestone         Target Date   Complete
             thanks to a strategic partnership between HKT    Agreement Finalization   Apr. 2025    100%
             Management, who manages Ben Thanh Plaza, the City   Design and Permitting
             of Arlington and the Arlington Economic Development   Completion
             Corporation (EDC). The goal of these improvements is   Begin Site
             to enhance tourism, improve the International Corridor   Improvements
             and foster a thriving, community-focused environment   Central Plaza &
             in the shopping center, which encompasses 13.1 acres   Infrastructure
             and houses around 50 stores and over a dozen dining   Construction
             options.                                         Commercial Building
                                                              Construction
             Through the agreement, HKT Management will make   Project Completion &   2  Qtr. FY 2027
                                                                                     nd
             property improvements including:                 Public Launch

                •  Resurfacing the parking lots
                •  Constructing an outdoor central plaza for
                   food trucks and events
                •  Improving landscaping
                •  Refreshing the interior and exterior of
                   buildings in Ben Thanh Plaza

             HKT Management will also construct a new 15,000-
             square-foot commercial building.

             This redevelopment effort aligns with the City’s
             International Corridor Visioning Effort, which
             establishes recommendations to guide improvements in
             the area, including lighting and walkability, enhancing
             aesthetics and identity and building community
             capacity.

             In exchange for these improvements with a minimum
             capital improvement expenditure of $3.6 million the
             Arlington EDC will reimburse up to $1.6 million for the
             costs of constructing infrastructure. The Owner will be
             required to complete all improvements within 21 months
             of signing the agreement and to maintain the property’s
             aesthetic appearance and cleanliness throughout the
             term of the agreement.