Page 112 - CityofArlingtonFY26AdoptedBudget
P. 112

Business Plan




                                       Strengthen Our Communities
                                                Protect Public Well-being

                          Project                   Performance Measure(s)                Department(s)
             Stormwater Projects              Implement Projects That Mitigate   Public Works
                                              Flooding Concerns

             Summary:
             Stormwater Projects are funded through the Stormwater Utility
             Fee and are included in the annual capital budget as well as in
             the Comprehensive Stormwater Master Plan.


             The projects listed below include major maintenance projects that began construction prior to FY 2026 as well as the
             planned FY 2026 construction projects. Project milestones listed in the table will be updated as they occur.


                                                                                             Linear Feet of
                      Stormwater Capital      Est. Bid   Actual    Estimated    Actual
                     Improvement Project       Date     Bid Date  Completion  Completion    Pipes/Channels
                                                                                              Constructed
                 2023 Miscellaneous Stormwater  Oct. 2023   Oct. 2023  Jan. 2026
                 Construction
                 2023 Outfall Improvements   Feb. 2026


             The projects listed below include major flood mitigation projects that began construction prior to FY 2026 as well as the
             planned FY 2026 construction projects. Project milestones listed in the table will be updated as they occur.

                                                              Actual                            Linear Feet of
                   Stormwater Capital   Structures   Est. Bid          Estimated     Actual
                  Improvement Project   Protected    Date      Bid     Completion  Completion   Pipes/Channels
                                                               Date                             Constructed
                Marquis Circle Drainage   2        Jan. 2026
                Improvements

                Harvest Hills Drainage   47        Aug. 2019
                Improvements Phase 1   (all phases)