                     CAPITAL IMPROVEMENT PROJECTS - COMMUNITY FACILITIES
                                                        2024-2029



         Park Master Plan Update and Projects
         Project Cost  $4,322,936
         Fiscal Year  Began working on identified projects in FY 2014-2015 - An updated to the plan is funded in FY20/21
                     The Park Master Plan was completed and approved in FY 2013-2014.  A five year plan has been composed
                     based on the Master Plan.  In FY 2014-2015 two dog parks and Phase one of the Skate Park was
                     constructed.  In FY2015-2016 Phase 2 of the skate park was constructed.  In FY2016-2017 a restroom was
         Description  placed at Willow Creek Park.  In FY2017-2018 parking lots were reconstructed and expanded at Willow
                     Creek Park. In FY2023/2024 the Kiwanis Veterans Park was relocated, improvements were made to the food
                     truck park,  and playground and shade structures were replaced at Highland Station Park.  In FY2024/2025
                     playground equipment will be replaced at Opal Jo Jennings and Brian Schwengler Parks.

         Impact on
         Operating   There are no additional operating costs as a result of these improvements.
         Budget

         Recreation Center Expansion
         Project Cost  Unknown
         Fiscal Year  Future Project
         Description  The existing recreation center facilities are in need of updating for space and use improvements.
         Impact on   We are expecting increases in Personal Services, Operating, and Contract Services expenditures when this
         Operating   project is completed.  However, because this is a future project and the scope is not known, we are not able
         Budget      to quantify the impact on the operating budget at this time.

         Library Relocation
         Project Cost  $20,400,000
         Fiscal Year  Design began in FY2021-2022 with construction estimated to be completed in summer of 2025.
                     The existing Library facilities are in need of updating for space and technological improvement.  The cost
         Description
                     estimate is for a 30,000 square foot facility.
         Impact on   We are expecting increases in Personal Services, Operating, and Contract Services expenditures when this
         Operating   project is completed.  Operating costs are estimated to be $152,535.
         Budget

         Public Works Facility
         Project Cost  Unknown
         Fiscal Year  Future Project
         Description  The existing public works facility is in need of updating for space and use improvements.
         Impact on   We can expect increases in operating expenditures when this project is completed.  However, because this
         Operating   is a future project and the scope is not known, we are not able to quantify the impact on the operating budget
         Budget      at this time.