CITY OF SAGINAW
                               CAPITAL IMPROVEMENT PROJECTS - WATER
                                                       2024-2029



              Old Decatur Rd 12" Water Line Phase 1
              Scope        West McLeroy Blvd to First Baptist Church
              Method       Open-cut
              Project Cost  $572,000
              Fiscal Year  Future CIP
                           This project would provide additional transmission capacity along Old Decatur Rd from
              Description  Longhorn Pump Station to the Wayside Elevated Tank.  This project could be constructed by
                           developers.
              Impact on    There will be an eventual increase in maintenance costs as this is a new water line.  As the
              Operating    infrastructure ages, estimated annual maintenance cost will be $2,576.
              Budget

              Northwest Booster Pump Station
              Scope        increase pressure to the northwest part of the City
              Method
              Project Cost  $432,500
              Fiscal Year  FY 2021-2022
                           The Northwest booster pump station will increase water pressure to the northwest part of the
              Description  City and provide domestic and fire flow capacity.  The pump station will be located a the
                           existing Park Center storage tank site.
              Impact on
              Operating    There will be no additonal operating or maintenance costs as a result of this upgrade.
              Budget


              Condor Trail 12" Water Line
              Scope        Dunster to Bailey Boswell Rd.
              Method       Open-cut
              Project Cost  $866,000
              Fiscal Year  Future CIP
                           This project will connect transmissions mains in Bailey Boswell with Heather Ride Estates and
              Description  provide distribution for future development.  The cost estimate assumes construction of the
                           water line before or concurrent with construction of new development.
              Impact on    There will be an eventual increase in maintenance costs as this is a new water line.  As the
              Operating    infrastructure ages, estimated annual maintenance cost will be $2,954.
              Budget

              Defiel Rd 8" Water Line
              Scope        Defiel Rd Cul-de-sac o Bailey Boswell Rd.
              Method       Open-cut
              Project Cost  $1,132,000
              Fiscal Year  Future CIP
                           This project will connect dead end distribution lines along Defiel Rd. with transmission mains
                           along Bailey Boswell.  This line will provide future distribution along Defiel Rd.The cost
              Description
                           estimate assumes construction of the water line before or concurrent with construction of new
                           development.
              Impact on    There will be an eventual increase in maintenance costs as this is a new water line.  As the
              Operating    infrastructure ages, estimated annual maintenance cost will be $2,819.
              Budget