CITY OF SAGINAW
                          CAPITAL IMPROVEMENT PROJECTS - WASTEWATER
                                                       2024-2029




             Fairmont 12" Sanitary Sewer Replacement
             Scope        Southern Ave. to Sansom Blvd.
             Method       Bore
             Project Cost  $3,333,000
             Fiscal Year  Phase 1 construction was completed in FY 2019-2020, phase 2 begin in FY2023/2024
                          This line was identified for replacement due to pipeline deterioration and inflow/infiltration
             Description  problems.  Replacing the new line by bore will minimize disturbance to railroad and industrial
                          activities.
             Impact on    Reduced operating costs are expected upon completion of this project.  Any savings in
             Operating    maintenance costs will be allocated to other locations in the wastewater system.  As the
             Budget       infrastructure ages, estimated maintenance cost will be $2,640.