Page 215 - CityofSaginawFY25Budget
P. 215

City of Saginaw
 Capital Improvement Plan
 2024-2029
 USE OF FUNDS                            SOURCE OF FUNDS
 Fixed Asset  Actual  Revised  Tarrant  Cap Proj  General  Escrow  Donations  Enterprise  Drainage  To Be
 Project Description  Note Prior Years 2023-2024  2024-2025  2025-2026  2026-2027  2027-2028  2028-2029  Future CIP  Total  County  Fund  Fund  Fund  Fund  Fund  Fund  Determined
 Fairmont 12" Sanitary Sewer Replacement  7052  73,000  84,500  3,175,500  0  3,333,000  3,333,000  0
 2,800 LF; Southern Ave to Sansom Blvd
 Total Wastewater System  73,000  84,500  3,175,500  0  0  0  0  0  3,333,000  0  0  0  0  0 3,333,000  0  0
 East Cement Creek Improvements Phase 2  6962  1,965,465  1,216,465  0  0  0  3,181,930  3,181,930  0
 Channel improvement Opal to Blueridge&Blueridge drainage
 East Cement Creek Improvements Phase 3  7080  423,206  300,673  0  0  0  0  723,879  723,879  0
 Channel to McLeroy (Blue Ridge St. Internal Drainage)
 Saginaw Blvd. System #3 Right of Way  9  75,000  0  75,000  75,000   0
 Easements, RR Permits, RR Inspection
 Saginaw Blvd. System #3 Ph. 1  2,500,000  2,500,000              2,500,000
 Saginaw Blvd. System #3 Ph. 2  1,500,000  1,500,000              1,500,000
 Saginaw Blvd. System #3 Ph. 3  310,000  310,000                   310,000
 Saginaw Blvd. System #3 Ph. 4  1,100,000  1,100,000              1,100,000
 Saginaw Blvd. System #3 TXDOT Review  10  750,000  750,000        750,000
 Total Drainage System  2,388,671  1,517,138  75,000  0  0  0  0  6,160,000  10,140,809  0  0  0  0  0  0 3,980,809  6,160,000
 Total Capital Projects  46,678,494 20,452,204 37,196,542  6,056,378  6,160,000  2,855,000  0  50,567,000 176,965,618 6,950,000  92,790,201 6,209,099 4,767,566  110,000 4,090,945 3,980,809  58,067,000
 Notes
 1 Project funded through cash reserves
 2 Includes two (2) grant applications to Texas Parks and Wildlife Department
 3 Project funded through Utility Impact Fees
 4 Projects constructed by City of Fort Worth
 5 Projects possible constructed by Developers
 6 Utility Relocation Project for TXDOT Highway Expansion
 7 Paid with Drainage Utility Reserves
 8 Paid with Cap Proj Reserves and Drainage Utility Fund
 9 Paid with Drainage Utility Fees
 10 On hold due to TXDOT Review Fee Issue

























                                                           205
   210   211   212   213   214   215   216   217   218   219   220