                                               Capital Project Request



                Department:    PUBLIC WORKS                           Date Prepared:   April 5,  2017
                Submitted By:   HAL CRANOR                            Date Completed:

                Project Title:   WELL  REPLACEMENT —   FULLER/  FAR NORTH
                Project Type:   WATER                  Sub -Type:   WELL
                Project CODE:   WT1802                 Priority:   A
                COUNCIL AUTHORIZATION:
                November 28,  2017:  Authorized  the City Manager to negotiate  and execute an Engineering  Design Contract with Alan
                Plummer Associates,  Inc.  for the design of two water wells to replace the existing Fuller Well and Far North Well.  The scope
                of work for this portion of the project includes the design of the above ground well facilities including  booster pumps,  electrical,
                and facilities required to operate the new wells.
                November 28,  2017:  Authorized the City Manager to execute an Engineering  Design Contract with RW Harden and
                Associates,  Inc. for the design of two water wells to replace the existing Fuller Well and Far North Well.  The scope of work for
                this portion of the project includes all below ground and associated work at the well facilities, the casing,  screen,  well head,
                and pump equipment.
                September 25,  2018:  Approved Resolution 18- 1537,  requesting financial assistance by authorizing an application to be filed
                with the Texas Water Development  Board for a Drinking Water State Revolving  Fund Loan.
                March 26,  2019:  Approved the first and final reading of Ordinance No.  2216,  authorizing the issuance of City of Euless,
                Texas,  Waterworks and Sewer System Revenue Bonds,  Series 2019.
                June 25,  2019:  Authorized award of Bid No.  003- 19,  for a construction contract to Weisinger Incorporated for well
                construction and plugging of the Far North and Fuller Wells in the amount of $6,426, 500,  less Change Order No.  1,  a
                deduction of $ 577, 400,  for a total net amount of $ 5, 849, 100.
                April 14,  2020:  Approved  award of Bid No.  002- 20 for a construction  contract to Felix Construction  Company for the
                construction of the Fuller and Far North Well project in the amount of $2, 631, 000.
                May 12,  2020:  Authorized  the City Manager to negotiate and execute an Engineering  Construction  Management  Agreement
                with Alan Plummer Associates.  The estimated expenditure is $ 121, 875 for basic services and a budget allowance of up to
                 40, 000 for additional services.
                August 3,  2020:  Authorized the City Manager to purchase and contract for the installation of two water well pumps,  motors,
                and associated appurtenances at the Far North and Fuller Wells,  in the amount of $ 542, 060,  through Weisinger,  Incorporated.
                August 11,  2020:  Authorized  the City Manager to execute a professional  services agreement  with Signature Automation,  LLC
                for Engineering Services at the Far North and Fuller Well sites.  The scope of services include:  Program Logic Control ( PLC)
                and Human Machine Interface ( HMI)  programming,  submittal  review for proposed equipment,  SCADA System testing,
                operations manuals and training.  The estimated expenditure is $ 73,540.
                October 12,  2021:  Authorized  a change order to the construction  contract with Felix Construction  Company for the above
                ground infrastructure and appurtenances portion of the Fuller and Far North Well project in the amount of $ 214, 074. 62.  The
                change order provides for additional  work including electrical  modifications,   piping,  painting,  concrete flat work,  and fencing.
                August 9,  2022:  Ratified City Manager action to proceed with emergency repairs to the City' s water wells at Fuller and Far
                North Well lots.  In order to maintain the existing warranty of the new wells,  Weisinger  Incorporated  will perform the work at an
                estimated expenditure of $417, 810.
                RELATIONSHIP TO OTHER PROJECTS AND/ OR MASTER PLAN:
                RW  Harden &   Associates completed a Preliminary Well Design Study in FY2017 in preparation for the replacement of the
                Fuller Well,  Far North Well,  and the eventual replacement of the 1400 North Main Well.
                PROJECT  DESCRIPTION:
                The project consists of the engineering design and complete replacement of the Fuller and Far North Wells with new 1, 800
                foot deep wells.
                PROJECT  SCHEDULE:
                Began Design:  January 2018
                Design Complete:  May 2019
                Began Construction:   July 2019
                Construction Complete:  May 2023

                JUSTIFICATION:
                RW  Harden &   Associates completed a Preliminary Well Design Study in FY2017 in preparation for the replacement of the
                Fuller Well,  Far North Well,  and the eventual replacement of the 1400 North Main Well.  The Fuller and Far North Well are in
                need of immediate replacement.  New wells will enable the City to provide high quality water to citizens while reducing
                maintenance and operational costs.



                Ordinance No.  2360,  Page 138 of 326