City of Euless

                                            Capital Project Request


                                                                                                   March  25, 2020
           Department:            PUBLIC  WORKS                                Date  Prepared:
           Submitted By:          HAL  CRANOR                                  Date  Completed:
           Project  Title:        LINE  REPLACEMENT —   HUNTINGTON    DRIVE  PHASE  I
           Project  Type:         WATER                       Sub - Type:   MAIN  REPLACEMENT

           Project Code:          WT2202                      Priority:   A
           COUNCIL  AUTHORIZATION:













           RELATIONSHIP   TO OTHER   PROJECTS   AND/ OR  MASTER   PLAN:
           The water mains included in this project are part of the City' s Water System Master Plan.










           PROJECT   DESCRIPTION:
           The project consists of the replacement of an existing 6 inch asbestos concrete water line located along East
           Alexander Lane from Dickey Drive to Huntington Drive and Huntington Drive between East Alexander Lane and
            East Huitt Lane.  Additionally,  replacement of lateral tie- ins located on Martin Lane and Slaughter Lane will be
            included  as well.







           PROJECT SCHEDULE:
            Began Design:  January 2022
            Design  Complete:   April  2023
           Anticipate Begin Construction:  July 2023
           Anticipate  Construction  Complete:   October  2023





           JUSTIFICATION:
           The line has had nine leaks repaired since 2007 and was installed in 1961.