PROJECT TITLE:  MISCELLANEOUS     VALVE REPLACEMENT                        PROJECT CODE:  WT1603

           NET EFFECTS ON OPERATING      AND                    TOTAL  ESTIMATED   CAPITAL  COST:
           MAINTENANCE    COST (+   OR -)  ANNUAL:

           Direct Operatina Cost                                Water  Valves

           Personnel:       Full Time (                         Minimum  balance $  150, 000)
                            Part Time $                       0
           Total Salary $                                     0
           Purchase of Services

           Materials &  Supplies
           Utilities






                                                              0
           Subtotal: $                                        0 Total Estimated Capital Cost

           Maintenance  Costs                                   Funding Source:
                                                                Transfer  from:
                                                                W/WW Operating Fund $                    285, 000
                                                                W/ WW CIP Fund Balance $                 230, 000
                                                              0

           Subtotal: $                                        0
          Annualexpense $                                     0


           Total Estimated Annual Cost                        0 Total Funding                            515, 000
                                                   CURRENT     STATUS
                                                                               OVER/ UNDER
           PHASE/ FUNDING  SOURCE                      BUDGET      EXPENDED     BUDGET (-+)           EXPENDED
          Engineering                                    10, 000 $      1, 305         8, 695              13%
          Contingency                                    10, 000 $          0         10, 000               0%
          Construction                                  495, 000 $    233, 186      261, 814               47%


















           TOTAL  PROJECT                               515, 000 $    234, 491      280, 509               46%