Utility Capital Projects
Project Name Project Description
Miscellaneous Water/Sewer This is an annual program that is completed by the Public Works Construction Division. The program
Main Replacement (2020) - will provide for water and sewer main replacements including any developmental projects. The project
Continuing Project replaces aging infrastructure and maintains high standards for water quality. This will include
replacements on the following streets: Oldham Place (Buckingham Trail - Yarmouth Avenue),
Shadydale Drive (Meadowview Ter. - Crosstimbers Lane), Southampton Road (Chapman Road -
Wakefield Road) and Susan Court (Scott Drive - 7533 Susan Court).
Miscellaneous Water/Sewer This is an annual program that is performed by the Public Works Construction Division. The program
Main Replacement (2021) - will provide for the construction of water and wastewater main replacements to include possible
Continuing Project development projects. The project replaces the aging and undersized water and wastewater
infrastructure. This year's scope is expected to include water/sewer main replacements on the
following streets: Edinburg Drive (Brookshire to Wakefield), Circle Drive (Susan Lee to Cul-de-sac),
Bogart (College Circle to Price), Spring Lea Way (Starnes to Lincoln) and Southampton Drive
(Wakefield to Chapman).
Motor Operated Transfer This project consists of motor operated valves to be placed on existing water lines at three locations
Valves - Continuing Project along Holiday Lane, Thaxton Parkway, and Boulevard 26.
Paramount Street Sanitary The is the 47th Year Community Development Block Grant (CDBG) Project. The project will consist of
Sewer (CDBG) - Continuing reconstructing approximately 1,900 linear feet of sanitary sewer main on the west and north sides of
Project Paramount Street.
Project Status: As of March 2022 bids have been received by Tarrant County. Construction
anticipated to begin spring 2022.
Sanitary Sewer System This project will consist of replacing approximately 1,200 linear feet of sanitary sewer main lines in
Rehabilitation (Various North Richland Hills. In addition five manholes will be replaced. Streets included in this project will be
Locations) - Continuing Nancy Lane (4900 to 5000 block); 8020 Laura Street to 8017 Lazy Street; and 7000 to 7028 Smithfield
Project Road.
SCADA Communication The Utility Division uses a Supervisory Control and Data Acquisition (SCADA) system to remotely
Replacement - Continuing monitor, make adjustments, and track trends within the water and wastewater system.
Project