Page 198 - Saginaw FY22 Adopted Annual Budget
P. 198
CITY OF SAGINAW
CAPITAL IMPROVEMENT PROJECTS - WATER
2020-2024
Bailey Boswell Rd 12" Water Line Loop
Scope Wagley Robertosn Rd. to Bailey Boswell Rd.
Method Open-cut
Project Cost $610,000
Fiscal Year Future CIP
This project will provide transmission for distribution lines for development on the
undeveloped property on the northeast corner of Bailey Boswell Rd. and Saginaw Blvd. The
Description
cost estimate assumes construction of the water line before or concurrent with construction of
new development.
Impact on There will be an eventual increase in maintenance costs as this is a new water line. As the
Operating infrastructure ages, estimated annual maintenance cost will be $2,816.
Budget
Longhorn Rd. & Old Decatur Rd. 8" Water Line Connection
Scope Lansdale Ln. to White Rock Dr.
Method Open-cut
Project Cost $420,000
Fiscal Year Future CIP
This project will provide additional transmission and looping along Longhrn Rd. and Old
Description
Decatur Rd.
Impact on
Operating There will be an eventual increase in maintenance costs as this is a new water line. As the
infrastructure ages, estimated annual maintenance cost will be $2,563.
Budget
192