Page 177 - Project Detail Sheet_AdoptedBook
P. 177

ADOPTED | BUDGET

                                                   Utility Capital Projects
                Department                                     Project Title                         Project Number
        Public Works                      Sewer Manhole Replacement and Rehabilitation Project (2021)     UT2104
                                                      Project Description
        This project will replace or rehabilitate roughly 150 wastewater manholes throughout the City. Staff has completed an inspection of
        approximately 5,500 manholes. Through this inspection process, it has been identified that 12% of the manholes (approximately
        660) need some form of replacement or rehabilitation. This project will be spread out over a 5 year period to complete all 660
        manholes.






                                                      Project Justification
        Through the inspection process of the wastewater manholes, staff assessed each manhole on overall structural condition,
        maintenance responsibility, and inflow/infiltration present. Each manhole was given a numerical grade on structural and
        maintenance condition, with inflow/infiltration being noted as observed or being present. All manholes were inspected by one staff
        member so grading would be consistent among all manholes. The manholes that makeup the 660 that need attention were graded
        poor and very poor. The majority of these manholes also were noted to have inflow/infiltration. Inflow/infiltration in the wastewater
        system causes many difficulties for the system. With rain events, the inflow/infiltration allows rainwater into the system causing
        capacity issues with the possibility of creating sanitary sewer overflows. The additional rainwater also creates additional wastewater
        flow to the treatment plants, which the City pays for in wastewater charges from the treatment plants. Brick manholes are a major
        factor with allowing inflow/infiltration into the wastewater system. Brick manholes are no longer a method of building manholes. The
        Department has identified three different rehabilitation techniques for this project. Each technique brings value to the project based
        on the need of the manhole that needs repair. The three techniques include: total reconstruction, cured-in-place fiberglass manhole
        liner, and sprayed epoxy manhole liner. After completion of the rehabilitation process of a manhole, the system will experience less
        inflow/infiltration due to rainwater and have less risk of a major wastewater issue resulting from a manhole collapse.
        Note: Project funding source is the Utility Fund (405).

        Project Schedule            Beginning Date   Ending Date        History          Fiscal Year   Amount
        Professional Services                                        Adopted Budget        2020-21       $250,000
        Engineering/Design                                               Total                           $250,000
        Land/ROW Acquisition
        Construction                     10/2020         09/2021
        Other
        Total Schedule                   10/2020         09/2021
        Sources of Funds             Appr. To Date  2021‐22 Budget  2022‐23 Estimate  2023‐Completion  Total Funding
        General Obligation Bonds
        Certificates of Obligation
        Federal/State Grants
        Reserves                         250,000              0                0               0         $250,000
        Sales Tax
        Other
        Total Funding                   $250,000             $0               $0              $0          $250,000

        Project Costs                  To Date    2021‐22 Budget  2022‐23 Estimate   2023‐Completion    Total Cost
        Professional Services
        Engineering/Design
        Land/ROW Acquisition
        Construction                     250,000               0               0               0          $250,000
        Other
        Total Costs                      $250,000             $0              $0              $0          $250,000
        Operating Impact
        No operating impact is anticipated.


        Fiscal Year                2020‐21       2021‐22      2022‐23       2023‐24       2024‐25     Total Impact
        Amount                           $0            $0            $0            $0            $0           $0



                                                             171

                                                                                                     NRH  | TEXAS
   172   173   174   175   176   177   178   179   180   181   182