Page 174 - Project Detail Sheet_AdoptedBook
P. 174

ADOPTED | BUDGET

                                                   Utility Capital Projects
                Department                                     Project Title                         Project Number
        Public Works                        Sanitary Sewer System Rehabilitation (Various Locations)      UT1703
                                                      Project Description
        This project will consist of replacing approximately 1,200 linear feet of sanitary sewer main lines in North Richland Hills. In addition
        five manholes will be replaced. Streets included in this project will be Nancy Lane (4900 to 5000 block);  8020 Laura Street to 8017
        Lazy Street; and 7000 to 7028 Smithfield Road.







                                                      Project Justification
        In 2010, the City conducted a Sanitary Sewer Assessment for the southern portion of the City (Project UT0902). The Study found
        that approximately 9,000 linear feet of sanitary sewer main lines are in need of replacement. The main lines are made of vitrified
        clay tile and have deteriorated to a point where pipe failures have occurred causing blockage and overflows. Many of the joint pipe
        sections are separated, allowing ground water and surface water intrusion resulting in capacity issues and added costs for the
        treatment of wastewater. This project will replace segments of the main lines by using the latest technology such as pipe bursting to
        eliminate the problem lines. The construction methods used will create minor inconveniences to residents. The result will be a more
        efficient, and safer sanitary sewer system in the southern portion of the City.  Approximately 1,200 linear feet of sanitary sewer lines
        will be replaced or repaired with this project.

        Project Status Update: Design is completed and staff is working to begin construction.

        Funding source: Utility Operations for Capital Projects.




        Project Schedule            Beginning Date   Ending Date        History          Fiscal Year   Amount
        Professional Services                                        Adopted Budget        2016-17       $150,000
        Engineering/Design                                               Total                           $150,000
        Land/ROW Acquisition
        Construction                     10/2016         09/2020
        Other
        Total Schedule                   10/2016         09/2020
        Sources of Funds             Appr. To Date  2021‐22 Budget  2022‐23 Estimate  2023‐Completion  Total Funding
        General Obligation Bonds
        Certificates of Obligation
        Federal/State Grants
        Reserves                         150,000              0                0               0         $150,000
        Sales Tax
        Other
        Total Funding                   $150,000             $0               $0              $0          $150,000

        Project Costs                  To Date    2021‐22 Budget  2022‐23 Estimate   2023‐Completion    Total Cost
        Professional Services
        Engineering/Design
        Land/ROW Acquisition
        Construction                     150,000               0               0               0          $150,000
        Other
        Total Costs                      $150,000             $0              $0              $0          $150,000
        Operating Impact
        No impact is anticipated.


        Fiscal Year                2020‐21       2021‐22      2022‐23       2023‐24       2024‐25     Total Impact
        Amount                           $0            $0            $0            $0            $0           $0