CITY OF KELLER FIVE-YEAR CAPITAL IMPROVEMENTS PROGRAM (CIP) SUMMARY



                                                           FISCAL YEARS
                                                                                                          TOTAL ALL
             PROJECT     PRIOR YEARS  FY 2020-21  FY 2021-22  FY 2022-23  FY 2023-24  FY 2024-25  FY 2025-26
                                                                                                           YEARS

                                                  WASTEWATER SYSTEM


                                               2019 Mains & Services Replacements
          Water-Wastewater
               Fund                   300,000                                                            $           300,000
          TOTAL PROJECT   $          300,000   $                     -   $                      -   $                    -   $                    -   $                     -   $                     -   $           300,000
           IMPACT ON O&M  The project replaces existing wastewater lines and minimal operating impact is anticipated.


                                            Big Bear West Interceptor Line Replacement
          Water-Wastewater                575,000                                                        $           575,000
               Fund
          TOTAL PROJECT   $          575,000   $                     -   $                      -   $                    -   $                    -   $                     -   $                     -   $           575,000
           IMPACT ON O&M  The project replaces existing wastewater lines and minimal operating impact is anticipated.


                                                   2019 SS Evaluation Study/I&I
          Water-Wastewater                240,000               120,000                120,000           $           480,000
               Fund
          TOTAL PROJECT   $          240,000   $          120,000   $           120,000   $                    -   $                    -   $                     -   $                     -   $           480,000

           IMPACT ON O&M  The project studies wastewater system needs and no direct operational costs are anticipated.


                                             2021 SS Evaluation Study/Capacity Analysis
          Water-Wastewater
               Fund                               180,000                                                $           180,000
          TOTAL PROJECT   $                      -   $          180,000   $                      -   $                    -   $                    -   $                     -   $                     -   $           180,000
           IMPACT ON O&M  The project studies wastewater system needs and no direct operational costs are anticipated.



                                          Cade Branch Wastewater Capacity Improvements
            Debt Issuance                                           2,415,600                            $        2,415,600
          Wastewater Impact
               Fees                                        2,415,600                                     $        2,415,600
          TOTAL PROJECT   $                      -   $                     -   $        2,415,600   $     2,415,600   $                    -   $                     -   $                     -   $        4,831,200
                         The project replaces existing wastewater lines and the operating impact relates to the average annual debt payment.
           IMPACT ON O&M
                                                                                   169,964              169,964              169,964



                                       Cade Branch Wastewater Capacity Improvements 8" to 15"
            Debt Issuance                                              946,200                           $           946,200
          Wastewater Impact                                   946,200                                    $           946,200
               Fees
          TOTAL PROJECT   $                      -   $                     -   $           946,200   $        946,200   $                    -   $                     -   $                     -   $        1,892,400
                         The project improves existing wastewater lines and the operating impact relates to the average annual debt payment.
           IMPACT ON O&M
                                                                                     66,576                66,576                66,576



                                                             365
   362   363   364   365   366   367   368   369   370   371   372