CITY OF KELLER FIVE-YEAR CAPITAL IMPROVEMENTS PROGRAM (CIP) SUMMARY



                                                           FISCAL YEARS
                                                                                                          TOTAL ALL
             PROJECT     PRIOR YEARS  FY 2020-21  FY 2021-22  FY 2022-23  FY 2023-24  FY 2024-25  FY 2025-26
                                                                                                           YEARS

                                                     WATER SYSTEM



                                                      SCADA Maintenance
          Water-Wastewater                        540,000                                                $           540,000
               Fund
          TOTAL PROJECT   $                      -   $          540,000   $                      -   $                    -   $                    -   $                     -   $                     -   $           540,000
           IMPACT ON O&M  The project is capital replacement of an existing equipment and minimal operating impact is anticipated.



                                                       Knox Tank Mixer
          Water-Wastewater                                    600,000                                    $           600,000
               Fund
          TOTAL PROJECT   $                      -   $                     -   $           600,000   $                    -   $                    -   $                     -   $                     -   $           600,000
           IMPACT ON O&M  The project is capital maintenance of an existing facility and minimal operating impact is anticipated.


                                                 Pearson Pump Station Generator

               Other                                       2,000,000                                     $        2,000,000
          TOTAL PROJECT   $                      -   $                     -   $        2,000,000   $                    -   $                    -   $                     -   $                     -   $        2,000,000
                         The project replaces existing water lines and the operating impact relates to the average annual debt payment.
           IMPACT ON O&M
                                                                                     91,469                91,469                91,469
                                                     Lift Station Generators

               Other                                          500,000                                    $           500,000
          TOTAL PROJECT   $                      -   $                     -   $           500,000   $                    -   $                    -   $                     -   $                     -   $           500,000
           IMPACT ON O&M  The project is installs generators at lift stations and minimal operating impact is anticipated.


                                                        MSC Generators
               Other                                          200,000                                    $           200,000
          TOTAL PROJECT   $                      -   $                     -   $           200,000   $                    -   $                    -   $                     -   $                     -   $           200,000

           IMPACT ON O&M  The project is capital replacement of an existing equipment and minimal operating impact is anticipated.


                                                  Bate Street Line Replacements
               Other                                          675,000                                    $           675,000
          TOTAL PROJECT   $                      -   $                     -   $           675,000   $                    -   $                    -   $                     -   $                     -   $           675,000
           IMPACT ON O&M  The project replaces existing water lines and minimal operating impact is anticipated.



                                                  Elm Street Line Replacements
               Other                                                1,375,000                            $        1,375,000
          TOTAL PROJECT   $                      -   $                     -   $                      -   $     1,375,000   $                    -   $                     -   $                     -   $        1,375,000
           IMPACT ON O&M  The project replaces existing water lines and minimal operating impact is anticipated.

                                                             361