Page 359 - Microsoft Word - FY 2021 tax info sheet
P. 359

CITY OF KELLER FIVE-YEAR CAPITAL IMPROVEMENTS PROGRAM (CIP) SUMMARY



                                                           FISCAL YEARS
                                                                                                          TOTAL ALL
             PROJECT     PRIOR YEARS  FY 2020-21  FY 2021-22  FY 2022-23  FY 2023-24  FY 2024-25  FY 2025-26
                                                                                                           YEARS

                                                      PARK SYSTEM



                                                  TBD Playground Replacement
             KDC Fund                                                              130,000              140,000              150,000   $           420,000
          TOTAL PROJECT   $                      -   $                     -   $                      -   $                    -   $         130,000   $         140,000   $         150,000   $           420,000
           IMPACT ON O&M  The project replaces existing playground equipment and minimal operating impact is anticipated.



                                         Keller Sports Park Parking Lot Improvements - A Pad
             KDC Fund                                                              380,000               $           380,000
          TOTAL PROJECT   $                      -   $                     -   $                      -   $                    -   $         380,000   $                     -   $                     -   $           380,000
           IMPACT ON O&M  The project improves an existing parking lot and minimal operating impact is anticipated.


                                         Keller Sports Park Parking Lot Improvements - D Pad

             KDC Fund                                                                         403,000    $           403,000
          TOTAL PROJECT   $                      -   $                     -   $                      -   $                    -   $                    -   $         403,000   $                     -   $           403,000
           IMPACT ON O&M  The project improves an existing parking lot and minimal operating impact is anticipated.


                                         Keller Sports Park Parking Lot Improvements - F Pad

             KDC Fund                                                                                    470,000   $           470,000
          TOTAL PROJECT   $                      -   $                     -   $                      -   $                    -   $                    -   $                     -   $         470,000   $           470,000
           IMPACT ON O&M  The project improves an existing parking lot and minimal operating impact is anticipated.


            TOTAL PARK
             SYSTEM       $       4,428,422   $       2,141,416   $        1,983,015   $     1,332,750   $         976,025   $      1,045,628   $      1,162,890   $      13,070,146




























                                                             357