CITY OF KELLER FIVE-YEAR CAPITAL IMPROVEMENTS PROGRAM (CIP) SUMMARY



                                                           FISCAL YEARS
                                                                                                          TOTAL ALL
             PROJECT     PRIOR YEARS  FY 2020-21  FY 2021-22  FY 2022-23  FY 2023-24  FY 2024-25  FY 2025-26
                                                                                                           YEARS

                                                      PARK SYSTEM



                                                  2017 Matching Grant Program
             KDC Fund                 100,000                 64,487                                     $           164,487
               Other                    50,680                                                           $             50,680
          TOTAL PROJECT   $          150,680   $            64,487   $                      -   $                    -   $                    -   $                     -   $                     -   $           215,167
                         The project funds new or enhanced park features with costs shared with a third party and any grant projects must have minimal operating
         IMPACT ON O&M
                         impact.

                                                        Milestone Park
             KDC Fund                 785,273                                                            $           785,273
          TOTAL PROJECT   $          785,273   $                     -   $                      -   $                    -   $                    -   $                     -   $                     -   $           785,273
           IMPACT ON O&M  The park improvements are considered passive use and have minimal operating impact.


                                                      Overton Ridge Park

             KDC Fund              2,464,655                                                             $        2,464,655
         Park Development Fees                84,594               463,062                               $           547,656
          TOTAL PROJECT   $       2,549,249   $          463,062   $                      -   $                    -   $                    -   $                     -   $                     -   $        3,012,311
                         The park improvements require additional mowing and other grounds maintenance.
           IMPACT ON O&M
                                                             $          27,808   $           27,808   $           27,808   $           27,808


                                                    Whitley Road Safe Routes
             KDC Fund                 248,312                                                            $           248,312
               Grant                                          680,515                                    $           680,515
          TOTAL PROJECT   $          248,312   $                     -   $           680,515   $                    -   $                    -   $                     -   $                     -   $           928,827

         IMPACT ON O&M   The project improves an existing trail and minimal operating impact is anticipated.


                                              2020 Parks Capital Replacement Program
             KDC Fund                 100,061                                                            $           100,061
          TOTAL PROJECT   $          100,061   $                     -   $                      -   $                    -   $                    -   $                     -   $                     -   $           100,061
           IMPACT ON O&M  The replacement program improves existing park features and equipment.  Minimal operating impact is anticipated.



                                               Bear Creek Bridge Erosion Protection
             KDC Fund                 409,847                                                            $           409,847
          TOTAL PROJECT   $          409,847   $                     -   $                      -   $                    -   $                    -   $                     -   $                     -   $           409,847
           IMPACT ON O&M  The trail improvements have minimal operating impact and can be absorbed in the current budget.